МАСЛЯНЫЙ НАСОС > УСТАНОВКА |
| 1. INSTALL WATER INLET PIPE |
![]() |
Apply soapy water to 2 new O-rings and install them to the inlet pipe.
Install the inlet pipe to the No. 1 heat exchanger cover.
| 2. INSTALL TIMING CHAIN COVER SUB-ASSEMBLY |
![]() |
Install a new oil pump gasket.
![]() |
Install a new O-ring.
Apply seal packing in a continuous line to the timing chain cover as shown in the following illustration.

![]() |
| Area | Seal packing diameter | Application position from inside edge of cover |
| Continuous Line Area | 3.0 to 4.0 mm (0.1181 to 0.1575 in.) | 2.5 mm (0.098 in.) |
| Dashed Line Area | 6.4 mm (0.2520 in.) or more, or within OK area shown in illustration | 0.5 mm (0.020 in.) |
| Diagonal Line Area | 3.0 to 4.0 mm (0.1181 to 0.1575 in.) | 5.5 mm (0.217 in.) |
![]() |
Align the oil pump's drive rotor spline and the crankshaft as shown in the illustration. Install the spline and chain cover to the crankshaft.
![]() |
Temporarily tighten the timing chain cover with the 30 bolts and nut.
| Item | Length | Thread diameter |
| Bolt A | 25 mm (0.984 in.) | 8 mm (0.315 in.) |
| Bolt B | 55 mm (2.165 in.) | 8 mm (0.315 in.) |
| Bolt C | 70 mm (2.756 in.) | 8 mm (0.315 in.) |
| Bolt D | 35 mm (1.378 in.) | 10 mm (0.394 in.) |
| Bolt E | 55 mm (2.165 in.) | 10 mm (0.394 in.) |
| Bolt F | 80 mm (3.150 in.) | 10 mm (0.394 in.) |
![]() |
Tighten the 11 bolts in several steps, in the sequence shown in the illustration.
![]() |
Temporarily tighten the belt tensioner with the standard bolt and 6 mm hexagon wrench bolt.
![]() |
Tighten the 21 bolts and nut in several steps, in the sequence shown in the illustration.
![]() |
![]() |
Install the 2 new gaskets and 2 plugs.
| 3. INSTALL CYLINDER HEAD COVER SUB-ASSEMBLY (for Bank 1) |
![]() |
Install 4 new gaskets and 2 new O-rings to the camshaft bearing caps (No. 2, No. 3, No. 7).
Install a new gasket to the cylinder head cover.
![]() |
Apply seal packing as shown in the illustration.
![]() |
Install the cylinder head cover with 2 new seal washers and the 15 bolts.
| 4. INSTALL CYLINDER HEAD COVER SUB-ASSEMBLY (for Bank 2) |
![]() |
Install 4 new gaskets and 2 new O-rings to the camshaft bearing caps. (No. 1, No. 3, No. 6).
Install a new gasket to the cylinder head cover.
![]() |
Apply seal packing as shown in the illustration.
![]() |
Install the cylinder head cover with 2 new seal washers and the 15 bolts.
| 5. INSTALL IGNITION COIL ASSEMBLY |
![]() |
Perform a visual inspection on the spark plug tube gasket
| Inspection Area | Inspection Result |
| Upper surface | No scratches or deformation |
| Outer lip | No scratches or deformation |
| Inner lip | No scratches |
![]() |
Set each spark plug tube gasket on each ignition coil.
![]() |
After installing each spark plug tube gasket, securely insert each ignition coil.
![]() |
Install the 8 bolts.
Connect the 8 ignition coil connectors.
| 6. INSTALL CRANKSHAFT PULLEY |
Align the pulley set key with the key groove of the pulley, and slide on the pulley.
![]() |
Using SST, install the pulley bolt.
| 7. INSTALL RESONATOR BRACKET SUB-ASSEMBLY |
![]() |
Install the resonator bracket with the bolt.
| 8. INSTALL OIL FILTER BRACKET |
![]() |
Install 2 new gaskets and the filter bracket with the 3 bolts.
| 9. INSTALL OIL FILTER ELEMENT |
![]() |
Clean the inside of the oil filter cap, the threads and O-ring groove.
Apply a small amount of engine oil to a new O-ring and install it to the oil filter cap.
Set a new oil filter element to the oil filter cap.
Remove any dirt or foreign matter from the installation surface of the engine.
Apply a small amount of engine oil to the O-ring again and temporarily install the oil filter cap.
![]() |
Using SST, tighten the oil filter cap.
![]() |
Apply a small amount of engine oil to a new drain plug O-ring, and install it to the oil filter cap.
Install the oil filter drain plug.
| 10. INSTALL CAMSHAFT TIMING CONTROL MOTOR ASSEMBLY (for Bank 1) |
![]() |
Turn the camshaft timing gear assembly's eccentric shaft index slot in the counterclockwise direction by hand, and set it to the maximum retard angle position.
Install a new O-ring to the timing chain cover.
![]() |
Align the joint of the camshaft timing control motor and the keyway of the camshaft timing gear assembly, and install the motor with the 3 bolts.
![]() |
Connect the 2 camshaft timing control motor connectors and engine wire clamp.
| 11. INSTALL CAMSHAFT TIMING CONTROL MOTOR ASSEMBLY (for Bank 2) |
![]() |
Turn the camshaft timing gear assembly's eccentric shaft index slot in the counterclockwise direction by hand, and set it to the maximum retard angle position.
Install a new O-ring to the timing chain cover.
![]() |
Align the joint of the camshaft timing control motor and the keyway of the camshaft timing gear assembly, and install the motor with the 3 bolts.
![]() |
Install the engine wire bracket with the bolt.
Connect the 2 camshaft timing control motor connectors.
| 12. INSTALL FRONT WATER BY-PASS JOINT |
![]() |
Install the water by-pass joint and 2 new gaskets with the 4 nuts.
| 13. INSTALL NO. 1 IDLER PULLEY SUB-ASSEMBLY |
![]() |
Install the bolt and idler pulley.
| 14. INSTALL NO. 2 IDLER PULLEY SUB-ASSEMBLY |
![]() |
Install the bolt and idler pulley.
| 15. INSTALL WATER PUMP PULLEY |
![]() |
Temporarily install the pulley with the 4 bolts.
Using SST, hold the pulley and tighten the 4 bolts.
| 16. INSTALL WATER INLET HOUSING |
![]() |
Install the inlet housing and new gasket with the 3 bolts.
![]() |
Using needle-nose pliers, grip the claws of the clips and slide the clips to connect the water by-pass hoses and water inlet hose.
| 17. INSTALL NO. 2 ENGINE COVER SUB-ASSEMBLY LH |
![]() |
Install the No. 2 engine cover sub-assembly LH.
| 18. INSTALL NO. 3 ENGINE COVER |
![]() |
Install the No. 3 engine cover.
| 19. INSTALL INTAKE MANIFOLD |
Install 2 new gaskets to the intake manifold.
![]() |
Temporarily install the intake manifold with the 2 nuts and 8 bolts. Then tighten the 2 nuts and 8 bolts uniformly in the order shown in the illustration.
![]() |
Connect the No.1 ventilation hose to the intake manifold.
| 20. INSTALL WATER BY-PASS PIPE SUB-ASSEMBLY |
![]() |
Install the water by-pass pipe to the intake manifold with the 2 bolts.
Connect the heater water inlet hose, heater water outlet hose, water inlet hose, and No. 3 water bypass hose to the water by-pass pipe with the 4 clamps.
| 21. INSTALL GENERATOR ASSEMBLY |
![]() |
Using an E8 "TORX" socket wrench, set the generator with the 2 stud bolts.
![]() |
Install the generator with the 2 bolts and 2 nuts.
![]() |
Connect the generator connector.
Connect the harness to the +B terminal with the nut.
| 22. INSTALL OIL LEVEL DIPSTICK GUIDE |
Apply a light coat of engine oil to a new O-ring.
Install the new O-ring to the guide.
![]() |
Install the dipstick guide with the 2 bolts.
Install the dipstick.
| 23. CONNECT COOLER COMPRESSOR ASSEMBLY |
![]() |
Connect the cooler compressor with the 2 stud bolts, 2 nuts and 2 bolts.
| 24. INSTALL EXHAUST MANIFOLD SUB-ASSEMBLY (for Bank 1) |
![]() |
Install a new gasket as shown in the illustration.
![]() |
Install the exhaust manifold to the cylinder head with the new 8 nuts in the order shown in the illustration.
| 25. INSTALL NO. 2 EXHAUST MANIFOLD HEAT INSULATOR |
![]() |
Install the heat insulator with the 3 bolts.
![]() |
Connect the sensor connector.
| 26. INSTALL NO. 2 STEERING INTERMEDIATE SHAFT ASSEMBLY (w/ VGRS) |
![]() |
Установите зажим на чехол выходного отверстия рулевой колонки.
![]() |
Совместите метки на промежуточном вале рулевого управления № 2 в сборе и рулевой колонке.
Вверните болт.
| 27. INSTALL NO. 2 STEERING INTERMEDIATE SHAFT ASSEMBLY (w/o VGRS) |
![]() |
Установите зажим на чехол выходного отверстия рулевой колонки.
![]() |
Совместите метки на промежуточном вале рулевого управления № 2 в сборе и главном вале рулевого управления.
Вверните болт.
| 28. INSTALL STEERING SLIDING YOKE WITH SHAFT SUB-ASSEMBLY (w/ VGRS) |
![]() |
Совместите метки на промежуточном вале рулевого управления № 2 в сборе и шлицевом хомуте рулевого вала в сборе.
Совместите метки на шлицевом хомуте рулевого вала в сборе и тяге рулевого управления.
Не затягивая, вверните болт (B).
![]() |
Вверните болт (A) и затяните болт (B).
| 29. INSTALL STEERING SLIDING YOKE WITH SHAFT SUB-ASSEMBLY (w/o VGRS) |
![]() |
Совместите метки на промежуточном вале рулевого управления № 2 в сборе и шлицевом хомуте рулевого вала в сборе.
Совместите метки на шлицевом хомуте рулевого вала в сборе и промежуточном вале рулевого управления в сборе.
Не затягивая, вверните болт (B).
![]() |
Вверните болт (A) и затяните болт (B).
| 30. INSTALL FRONT SUSPENSION MEMBER REINFORCEMENT LH |
![]() |
Установите левое усиление элемента передней подвески на автомобиль и закрепите его 4 болтами.
| 31. CONNECT FRONT STABILIZER BAR |
![]() |
Подсоедините штангу стабилизатора к задней скобе и закрепите ее 4 болтами.
| 32. INSTALL FRONT EXHAUST PIPE ASSEMBLY |
Install the front exhaust pipe (see page Нажмите здесь).
| 33. CONNECT ENGINE WIRE |
![]() |
Connect the engine wire with the 4 nuts.
Connect the clamp and install the 2 clamp brackets with the 2 bolts.
Connect the intake air control valve actuator connector.
Connect the No. 1 vacuum switching valve connector.
![]() |
Connect the ground wire with the bolt.
![]() |
for Engine Room RH Side:
Connect the 2 clamps and install the 3 clamp brackets with the 3 bolts.
Connect the engine oil level sensor connector.
Connect the crankshaft position sensor connector.
Connect the starter connector and starter wire with the nut.
Connect the generator connector and generator wire with the nut.
Connect the camshaft position sensor connector.
Connect the engine wire connector.
Connect the 2 camshaft timing control motor connectors. (for Bank 2)
Connect the 2 VVT sensor connectors.
Connect the 4 ignition coil connectors.
Connect the camshaft timing control valve connector.
![]() |
Connect the wires with No. 1 engine room junction block with the 2 nuts.
![]() |
Connect the 3 connectors with front controller with the clamp.
![]() |
for Engine Room LH Side:
Install the clamp bracket with the bolt.
Connect the 3 clamps and 3 ground wires with the 3 bolts.
Attach the clamp and connect the cooler compressor connector.
Connect the 2 camshaft timing control motor connectors. (for Bank 1)
Connect the engine oil pressure sensor connector.
Connect the engine coolant temperature sensor connector.
![]() |
Connect the clamp and install the 2 clamp brackets with the 2 bolts.
Connect the No. 8 engine wire connector.
Connect the 2 VVT sensor connectors.
Connect the 4 ignition coil connectors.
Connect the camshaft timing control valve connector.
![]() |
Connect the 3 ECT connectors and 4 ECM connectors.
Install the ECM box cover (upper).
| 34. INSTALL ENGINE ROOM ECU OUTLET DUCT |
![]() |
Install the outlet duct.
| 35. INSTALL SKID CONTROL ECU BRACKET |
![]() |
Установите кронштейн, закрепив его болтом и 2 гайками.
| 36. INSTALL SKID CONTROL ECU |
![]() |
Подсоедините 2 разъема (A) и нажмите рычаги блокировки вниз, чтобы зафиксировать разъемы.
Подсоедините разъем (В).
![]() |
Установите ЭБУ и закрепите его 2 болтами (C) и гайкой (D).
Подсоедините короткозамыкатель имитатора хода педали тормоза (E) к кронштейну ЭБУ системы противоскольжения.
| 37. CONNECT NO. 2 RADIATOR HOSE |
| 38. CONNECT NO. 1 RADIATOR HOSE |
| 39. INSTALL V-RIBBED BELT |
![]() |
Install the V belt as shown in the illustration.
Rotate the tensioner pulley counterclockwise, and then remove the fix bar.
| 40. INSTALL RADIATOR RESERVOIR ASSEMBLY |
Install the radiator reservoir with the 2 bolts.
![]() |
Connect the 2 reservoir hoses.
| 41. INSTALL AIR CLEANER ASSEMBLY LH |
![]() |
Install the air cleaner case with the 2 nuts and clip.
Install the air cleaner element to the air cleaner case.
![]() |
Install the air cleaner cap with the 2 clamps.
Connect the MAF meter connector.
| 42. INSTALL AIR CLEANER ASSEMBLY RH |
![]() |
Install the air cleaner case with the 2 nuts and clip.
Install the air cleaner element to the air cleaner case.
![]() |
Install the air cleaner cap with the 2 clamps.
Connect the MAF meter connector.
| 43. INSTALL INTAKE AIR CONNECTOR PIPE |
![]() |
Align the protrusion of the intake air resonator with the cutout of the bracket and insert the protrusion.
Install the intake air connector pipe with the 3 hose clamps.
![]() |
Connect the No. 1 ventilation hose and No. 2 ventilation hose to the intake air connector pipe.
| 44. INSTALL NO. 1 AIR CLEANER INLET |
![]() |
Align the holes with the connection areas labeled A, and attach the No. 1 air cleaner inlet.
![]() |
Install the No. 1 air cleaner inlet with the 2 bolts.
| 45. INSTALL ENGINE UNDER COVER REAR LH |
![]() |
Установите левую заднюю защиту картера двигателя и закрепите ее 2 винтами.
| 46. INSTALL ENGINE UNDER COVER REAR RH |
| 47. INSTALL BATTERY TRAY |
Install the battery tray with the 3 bolts.
Install the battery and battery insulator.
| 48. INSTALL BATTERY CLAMP SUB-ASSEMBLY |
Install the battery clamp and 2 clamp bolts with the nut.
| 49. ADD ENGINE OIL |
Add fresh oil.
| Oil grade | Oil Viscosity (SAE) |
| API grade SL or SM multigrade engine oil | - 0W-20 - 5W-20 - 5W-30 - 10W-30 - 15W-40 - 20W-50 (0W-20 is best choice for fuel economy and good starting in cold weather.) |
| Item | Specified Condition |
| Drain and refill with oil filter change | 8.6 liters (9.1 US qts, 7.6 Imp. qts) |
| Drain and refill without oil filter change | 8.4 liters (8.9 US qts, 7.4 Imp. qts) |
| Dry fill | 10.2 liters (10.8 US qts, 9.0 Imp. qts) |
Install the oil filler cap.
![]() |
Close the oil filler cap service hole cover.
| 50. ADD ENGINE COOLANT |
Tighten the radiator drain cock plug and 2 cylinder block drain cock plugs.
Add TOYOTA Super Long Life Coolant (SLLC) into the radiator reservoir.
![]() |
Further add coolant into the reservoir until it reaches the FULL line.
Press the No. 1 and No. 2 radiator hoses several times by hand, and then check the coolant level.
If the coolant level is low, add coolant.
![]() |
Using a 6 mm hexagon wrench, install the vent plug.
Bleed air from the cooling system.
While idling the engine for approximately 10 minutes, make sure the coolant remains at the FULL line by adding coolant as necessary.
![]() |
After idling the engine for 10 minutes, add coolant until it reaches the B line at the base of the reservoir's filler neck.
Close the radiator reservoir cap, and run the engine at 1500 to 2000 rpm for 5 minutes.
Stop the engine and wait until the coolant cools down to ambient temperature.
![]() |
Check the coolant level.
If the coolant level is below the FULL line, add coolant until it reaches the FULL line.
| 51. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL |
| 52. PERFORM INITIALIZATION |
Perform initialization (see page Нажмите здесь).
| 53. INSPECT FOR OIL LEAK |
Inspect for engine oil leak (see page Нажмите здесь).
| 54. INSPECT FOR COOLANT LEAK |
![]() |
Fill the radiator with coolant and attach a radiator cap tester.
Warm up the engine.
Using the radiator cap tester, increase the pressure inside the radiator to 118 kPa (1.2 kgf/cm2, 17 psi), and check that the pressure does not drop.
If the pressure drops, check the hoses, radiator and water pump for leaks. If no external leaks are found, check the heater core, cylinder block and head.
| 55. INSPECT FOR EXHAUST GAS LEAK |
If gas is leaking, tighten the areas necessary to stop the leak. Replace the damaged parts as necessary.
| 56. CHECK ENGINE OIL LEVEL |
Warm up the engine, stop the engine and wait 5 minutes. The oil level should be between the dipstick's low level mark and full level mark.
If low, check for leakage and add oil up to the full level mark.
| 57. INSTALL FRONT SUSPENSION MEMBER PROTECTOR LOWER |
![]() |
Install the suspension member protector with the 8 bolts.
| 58. INSTALL NO. 2 ENGINE UNDER COVER |
![]() |
Install the under cover with the 8 bolts.
| 59. INSTALL NO. 1 ENGINE UNDER COVER |
![]() |
Install the cover with the 7 clips and 13 screws.
| 60. INSTALL ENGINE ROOM SIDE COVER RH |
![]() |
Install the side cover with the 4 clips.
| 61. INSTALL ENGINE ROOM SIDE COVER LH |
![]() |
Install the side cover with the 4 clips.
| 62. INSTALL AIR CLEANER INLET COVER SUB-ASSEMBLY |
![]() |
Attach the 4 clips B.
Install the air cleaner inlet cover with the 5 clips A.
| 63. INSTALL V-BANK COVER SUB-ASSEMBLY |
![]() |
After sliding the cover from the vehicle front to the rear to attaching the 2 clips A, attach the 4 clips B and install the V bank cover.
| 64. INSTALL COWL TOP VENTILATOR LOUVER RH |
![]() |
Install the 6 clips and cowl top ventilator louver RH.