STEP 2. M.U.T.-IIISE ETACS system data list
Check the input signal of ACC relay.- Turn the ignition switch to the "ACC" position.
| | | Item No. | Item name | Normal condition | | 111 | ACC switch | ON |
|
OK: Normal condition is displayed.
Is the check result normal?
Go to Step 3.
Refer to ETACS - Inspection Procedure 1 "The ignition switch (ACC) signal is not sent to the ETACS-ECU
."
STEP 3. Voltage measurement at DC/DC converter (Entertainment) connector (IGN terminal).
(1) Disconnect the connector, and measure at the wiring harness side.
(2) Turn the ignition switch to the "ACC" position.
(3) Check the voltage between DC/DC converter (Entertainment) connector (IGN terminal) and body earth.OK: System voltage
Is the check result normal?
Go to Step 5.
Go to Step 4.
STEP 4. Check of short to power supply, short to earth, and open circuit in IGN line between DC/DC converter (Entertainment) connector and ETACS-ECU connector
STEP 5. Voltage measurement at DC/DC converter (Entertainment) connector (PWR terminal).
(1) Disconnect the connector, and measure at the wiring harness side.
(2) Check the voltage between DC/DC converter connector (PWR terminal) and body earth.OK: System voltage
Is the check result normal?
Go to Step 7.
Go to Step 6.
STEP 6. Check of short to power supply, short to earth, and open circuit in PWR line between fusible link and DC/DC converter (Entertainment) connector.
STEP 7. Resistance measurement at DC/DC converter connector (GND terminal).
(1) Disconnect the connector, and measure at the wiring harness side.
(2) Check the continuity between the DC/DC converter connector (GND terminal) and body earth.OK: Continuity exists (2 Ω or less)
Is the check result normal?
No action is necessary and testing is complete.
Go to Step 8.
STEP 8. Check of open circuit in GND line between DC/DC converter connector and body earth.