CANISTER > INSPECTION

for Preparation Click here



1. INSPECT CHARCOAL CANISTER ASSEMBLY


    A067137
  1. Visually check the charcoal canister for cracks or damage.



    A067138E04
  1. Inspect the charcoal canister operation.

    1. Blow air (0.39 kPa, 4.0 gf/cm2, 0.06 psi) into the vent port with the purge port closed, and check that the air flows from the air inlet port.



    2. A067139E03
    3. Blow air (0.39 kPa, 4.0 gf/cm2, 0.06 psi) into the vent port with the air inlet port closed, and check that air flows from the purge port.



    4. A067140E04
    5. Apply vacuum (3.43 kPa, 25.7 mmHg, 1.01 in.Hg) to the vent port with the air inlet port closed, and check that air is sucked in from the purge port.
      If operation is not as specified, replace the charcoal canister.



    A067141E05
  1. Inspect the air tightness.

    1. Apply vacuum (3.43 kPa, 25.7 mmHg, 1.01 in.Hg) to the purge port with the vent and air inlet ports closed, and check that the vacuum is sustained for 1 minute.

      HINT:
      In order to maintain air tightness, the check should be performed with the CCV terminal port held closed by hand.

      If operation is not as specified, replace the charcoal canister.



    A067142E06
  1. Inspect the diaphragm.

    1. Remove the air hose between ports A and B.

    2. Apply vacuum (1.42 kPa, 11 mmHg, 0.42 in.Hg) into port A with the vent, purge and air inlet ports closed, and check that air is sucked in from port B.



    3. A067143E05
    4. Apply vacuum (1.42 kPa, 11 mmHg, 0.42 in.Hg) into port A with the vent, purge and air inlet ports closed, and measure how long it takes for the vacuum to drop.

      Vacuum drop time:
      10 seconds or more

      If operation is not as specified, replace the charcoal canister.

    5. Reinstall the air hose between ports A and B.



    A074866E06
  1. Inspect VSV for open circuit.

    1. Using an ohmmeter, check that there is continuity between the terminals.

      Resistance:
      20°C (68°F)
      100°C (212°F)
      25 to 30 Ω
      32 to 42 Ω

      If there is no continuity, replace the charcoal canister.



    A074867E06
  1. Inspect VSV operation.

    1. Check that air flows from ports A to B and C.



    2. A074868E07
    3. Apply battery positive voltage across the terminals.

    4. Check that the valve is closed.



    5. A074869E04
    6. Check that air does not flow from ports A to B.

    7. Check that air flows from ports A to C.
      If the operation is not as specified, replace the charcoal canister.