CANISTER > INSPECTION |
| 1. INSPECT CANISTER ASSEMBLY |
![]() |
Visually check the canister assembly for cracks or damage.
If cracks or damage is found, replace the canister assembly.
![]() |
Check the canister operation.
With the purge port and connector closed, blow 5 kPa (0.1 kgf/cm2, 0.7 psi) of air into the vent port, and check that air flows from the air inlet port.
| *1 | Vent Port |
| *2 | Purge Port |
| *3 | Air Inlet Port |
| *4 | Connector |
![]() | Air |
![]() |
With the vent port and connector closed, blow 5 kPa (0.1 kgf/cm2, 0.7 psi) of air into the air inlet port, and check that air flows from the purge port.
| *1 | Vent Port |
| *2 | Purge Port |
| *3 | Air Inlet Port |
| *4 | Connector |
![]() | Air |
![]() |
Check for air leaks.
Connect a pressure gauge to the vent port of the canister.
| *1 | Vent Port |
| *2 | Purge Port |
| *3 | Air Inlet Port |
| *4 | Pressure Gauge |
| *5 | Connector |
With the purge port, air inlet port and connector closed, apply 19.6 kPa (0.2 kgf/cm2, 2.81 psi) of pressurized air into the vent port, and then confirm that pressure is retained for 1 minute.
If the result is not as specified, replace the canister assembly.