Home › Vehicle Exterior › EXTERIOR PANELS / TRIM › ROOF DRIP SIDE FINISH MOULDING

ROOF DRIP SIDE FINISH MOULDING > INSTALLATION

for Preparation Click here


HINT:
  1. Use the same procedure for both the RH and LH sides.
  2. The following procedure is for the LH side.



1. INSTALL NO. 1 ROOF DRIP SIDE FINISH MOULDING CLIP

NOTICE:
  1. If reusing the clips, do not remove the double-sided tape remaining on the clips and where the clips will be installed on the body.
  2. If installing new clips, remove the double-sided tape remaining where the clips will be installed on the body and clean the body with a non-residue solvent.



    B229383E02
  1. Apply a 2 to 3 mm (0.0787 to 0.118 in.) bead of adhesive (3M DP-105 or equivalent) to new No. 1 roof drip side finish moulding clip.
    Text in Illustration  
    *1
    Adhesive
    *a
    2 to 3 mm (0.0787 to 0.118 in.) Bead of Adhesive

    HINT:
    Adhesive strength (tensile strength): 13.7 MPa (140 kgf/cm2, 1987 psi) or more (when the temperature is 23°C (73°F)).

  1. Press and install the No. 1 roof drip side finish moulding clip.



  1. Install the clips to the positions on the roof panel shown in the illustration. Determine the locations and firmly press and install the No. 1 roof drip side finish moulding clip after lightly applying adhesive (3M DP-105 or equivalent).


    B313069E01


    Standard Dimension:

    Area
    Dimension
    a
    2.0 mm (0.0787 in.)
    b
    26.2 mm (1.0315 in.)
    c
    20.5 mm (0.8071 in.)


    Text in Illustration 
    *1
    Out Side Panel
    *2
    Roof Panel

  1. Install the roof drip center side finish moulding when 40 minutes or more have elapsed after pressing and installing the No. 1 roof drip side finish moulding clips.

    HINT:
    1. Initial hardening time: 40 minutes
    2. Complete hardening time: 24 hours



2. INSTALL CENTER ROOF DRIP SIDE FINISH MOULDING


    B313068
  1. Engage the 2 clips and install the center roof drip side finish moulding, as shown in the illustration.