2011-2016 FJ Cruiser · Service Manual ENGINE

INSTALLATION

Removal / installation · Vehicles built Aug 2009 – Jul 2014

Versions by build date: Jul 2007 – Jul 2009 Aug 2009 – Jul 2014 from Aug 2014


1. INSTALL VENTILATION VALVE SUB-ASSEMBLY
  1. Apply adhesive to 2 or 3 threads of the ventilation valve.

    Adhesive:
    Toyota Genuine Adhesive 1324, Three Bond 1324 or equivalent

  1. Install the ventilation valve.

    Torque:
    27 N*m{ 275 kgf*cm , 20 ft.*lbf }

  1. Connect the ventilation hose to the ventilation valve.

  1. Secure the ventilation hose with the clamp.


2. CONNECT HEATER HOSE
  1. Connect the heater hose clamp.


3. INSTALL V-BANK COVER
  1. Engage the 2 V-bank cover hooks to the bracket.

  1. Align the 2 V-bank cover grommets with the 2 pins and press down on the V-bank cover to engage the pins.