Home › ENGINE › 1GR-FE EMISSION CONTROL › PCV VALVE

PCV VALVE > INSTALLATION

for Preparation Click here



1. INSTALL VENTILATION VALVE SUB-ASSEMBLY
  1. Apply adhesive to 2 or 3 threads of the ventilation valve.

    Adhesive:
    Toyota Genuine Adhesive 1324, Three Bond 1324 or equivalent

  1. Install the ventilation valve.

    Torque:
    27 N*m{ 275 kgf*cm , 20 ft.*lbf }

  1. Connect the ventilation hose to the ventilation valve.

  1. Secure the ventilation hose with the clamp.



2. CONNECT HEATER HOSE
  1. Connect the heater hose clamp.



3. INSTALL V-BANK COVER
  1. Engage the 2 hooks and install the V-bank cover to the No. 1 V-bank cover bracket.

  1. Align the 2 V-bank cover grommets with the 2 pins and press down on the V-bank cover to engage the pins.