HEADLIGHT ASSEMBLY > INSTALLATION |
| 1. INSTALL HEADLIGHT ASSEMBLY (Body Type Wide) |
![]() |
Connect each connector.
Engage the 2 claws.
Install the headlight assembly with the 2 screws and the pin.
| 2. INSTALL HEADLIGHT ASSEMBLY (Body Type Narrow) |
![]() |
Attach protective tape to the position shown in the illustration.
Connect each connector.
Engage the 2 claws.
Install the headlight assembly with the 2 screws and the pin.
| 3. INSTALL FRONT BUMPER SIDE SUPPORT (Body Type Wide) |
| 4. INSTALL FRONT BUMPER ASSEMBLY (Body Type Wide) |
| 5. INSTALL STEP PLATE COVER LH (Body Type Wide) |
| 6. INSTALL STEP PLATE COVER RH (Body Type Wide) |
| 7. INSTALL RADIATOR GRILLE |
| 8. VEHICLE PREPARATION FOR HEADLIGHT AIM ADJUSTMENT |
Prepare the vehicle:
| 9. PREPARATION FOR HEADLIGHT AIMING (Using a screen) |
![]() |
Prepare the vehicle according to the following conditions:
Prepare a piece of thick white paper (approximately 2 m (6.6 ft) (height) x 4 m (13.1 ft) (width)) to use as a screen.
Draw a vertical line down the center of the screen (V line).
Set the screen as shown in the illustration.

![]() |
Draw base lines (H line, V LH, V RH lines) on the screen as shown in the illustration.
H Line (Headlight height):
V LH Line, V RH Line (Center mark position of left-hand (LH) and right-hand (RH) headlights):
| 10. HEADLIGHT AIMING INSPECTION |
Cover or disconnect the connector of the headlight on the opposite side to prevent light from the headlight not being inspected from affecting headlight aiming inspection.
Start the engine.
With headlight leveling switch:
Set the headlight leveling switch to 0 (zero).
Turn on the headlight and make sure that the cutoff line falls within the specified area, as shown in the illustration.

| 11. HEADLIGHT AIMING ADJUSTMENT |
![]() |
Adjust the aim vertically:
Adjust the aim horizontally:
| 12. VEHICLE PREPARATION FOR FOG LIGHT AIM ADJUSTMENT |
Prepare the vehicle:
| 13. PREPARATION FOR FOG LIGHT AIMING |
![]() |
Prepare the vehicle according to the following conditions:
Prepare a piece of thick white paper (approximately 2 m (6.6 ft) (height) x 4 m (13.1 ft) (width)) to use as a screen.
Draw a vertical line down the center of the screen (V line).
Set the screen as shown in the illustration.

![]() |
Draw base lines (H line, V LH, V RH lines) on the screen as shown in the illustration.
H Line (Fog light height):
V LH Line, V RH Line (Center mark position of left-hand (LH) and right-hand (RH) fog lights):
| 14. FOG LIGHT AIMING INSPECTION |
Cover or disconnect the connector of the fog light on the opposite side to prevent light from the fog light not being inspected from affecting fog light aiming inspection.
Start the engine.
Turn on the fog light and make sure that the cutoff line falls within the specified area, as shown in the illustration.

| 15. FOG LIGHT AIMING ADJUSTMENT |
![]() |
Adjust the fog light aim into the specified range by turning the aiming screw with a screwdriver.