Home › HEATER & AIR CONDITIONING SYSTEM › AIR CONDITIONING › BLOWER UNIT

BLOWER UNIT > INSTALLATION

for Preparation Click here



1. INSTALL BLOWER UNIT


    E107714
  1. Install the wire harness with the screw. (w/ PTC)



    E107304E03
  1. Install the blower unit with the 4bolts.

  1. Install the 2 clamps and 2 connectors.

  1. Install the 2 connectors. (w/ PTC)



    E111321
  1. Install the junction block with the nut. (body type narrow)



    E104261
  1. Install the junction block with the 2 nuts.(RHD)



2. INSTALL AIR DUCT NO.2


    E107299E01
  1. Engage the 2 claws to install the air duct No.2.



3. INSTALL STEERING INTERMEDIATE SHAFT
  1. Align the matchmarks on the steering intermediate shaft assembly No.2 and the steering gear assembly.



    C102131E01
  1. Temporarily install the bolt.



4. INSTALL STEERING COLUMN ASSEMBLY


  1. Temporarily install the steering column assembly with the 3 bolts.


    C106048E01

  1. Fully tighten the 3 bolts on the steering column assembly.

    Torque:
    21 N*m{ 214 kgf*cm , 16 ft.*lbf }

  1. Fully tighten the bolt on the steering intermediate shaft assembly No.2.

    Torque:
    36 N*m{ 367 kgf*cm , 27 ft.*lbf }

    NOTICE:
    Ensure that the steering column assembly is in the lowermost tilt position.

  1. Connect the connectors and clamp the wire harness to the steering column assembly bracket.



    C102130
  1. Install the steering shaft cover with the 3 bolts.

    Torque:
    8.0 N*m{ 82 kgf*cm , 71 in.*lbf }



5. INSTALL INSTRUMENT PANEL ASSEMBLY

HINT:
. Refer to the instruction for removal of the instrument panel assembly.



6. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL


7. PERFORM INITIALIZATION

HINT:
Some systems need initialization when disconnecting the cable from the negative battery terminal. (Click here)