INSTALLATION
Removal / installation · Vehicles built Apr 2016 – Dec 2016
Versions by build date: Oct 2014 – Dec 2014 Jan 2015 – Mar 2016 Apr 2016 – Dec 2016 from Jan 2017
| 1.
INSTALL STARTER ASSEMBLY |
 |
- Install the starter with the bolt and 2 nuts.
-
Torque:
- 68 N*m{
693 kgf*cm
, 50 ft.*lbf
}
- Connect the wire harness to terminal 30 and install the nut.
-
Torque:
- 9.8 N*m{
100 kgf*cm
, 87 in.*lbf
}
Close the terminal cap.
Connect the terminal 50 connector to the starter assembly.
- for Wide body:
Install the ground cable with the bolt.
-
Torque:
- 25 N*m{
250 kgf*cm
, 18 ft.*lbf
}
| 2.
INSTALL TRANSMISSION CONTROL CABLE BRACKET NO.1 (for Automatic Transmission)
|
 |
- Install the transmission control cable bracket No.1 to the automatic transmission assembly with the 2 bolts.
-
Torque:
- 28 N*m{
286 kgf*cm
, 21 ft.*lbf
}
| 3.
INSTALL TRANSMISSION CONTROL CABLE ASSEMBLY (for Automatic Transmission)
|
 |
- Fix the transmission control cable assembly to the control cable bracket with a clip.
Install the transmission control cable assembly to the control shaft lever with the nut.
-
Torque:
- 15 N*m{
150 kgf*cm
, 11 ft.*lbf
}
| 4.
INSTALL ENGINE SIDE UNDER COVER LH (w/ Engine Side Under Cover LH) |
 |
-
Torque:
- 13 N*m{
133 kgf*cm
, 10 ft.*lbf
}
| 5.
INSTALL ENGINE SIDE UNDER COVER RH (w/ Engine Side Under Cover RH) |
 |
-
Torque:
- 13 N*m{
133 kgf*cm
, 10 ft.*lbf
}
| 6.
INSTALL ENGINE UNDER COVER NO.2 (w/ Engine Under Cover No.2) |
 |
-
Torque:
- 13 N*m{
133 kgf*cm
, 10 ft.*lbf
}
| 7.
CONNECT NEGATIVE BATTERY CABLE |
|
| 8.
PERFORM INITIALIZATION |
 |
Some system need initialization when reconnecting the battery cable. (Click here)