Home › ENGINE ยท 1KD-FTV › ENGINE CONTROL SYSTEM › ECD SYSTEM (w/ EGR Cooler)

ECD SYSTEM (w/ EGR Cooler) > INITIALIZATION

for Preparation Click here


HINT:
After replacing the supply pump and/or the ECM:
  1. If the engine is defective or stalls immediately after startup, the ECM's learned values must be initialized. The engine can be initialized through the intelligent tester or by short-circuiting DLC3 terminals.
  2. If the engine starts normally, initialization is not necessary. Perform step the "idle the engine" procedure below only.


SUPPLY PUMP INITIALIZATION PROCEDURE


    A141744E01
  1. Connect the intelligent tester to the DLC3.

  2. Turn the ignition switch ON.

    NOTICE:
    Do not start the engine.

  3. Turn the tester ON.

  4. Enter the following menus: Powertrain / Engine / Utility / Supply Pump Initialization.

  5. Press "Next".



  6. A141745E01
  7. Press "Next".



  8. A141746E01
  9. Press "Exit".

  10. Start the engine to check if the initialization is complete. If the engine cannot be started, repeat the initialization procedures from the beginning.

  11. Idle the engine for at least 1 minute under the following conditions (Procedure "A"):

    1. The water temperature is 60°C (140°F) or more.
    2. The fuel temperature is 20°C (68°F) or more.

    NOTICE:
    Do not race the engine immediately after starting the engine. After warming up the engine, racing the engine is acceptable.

    HINT:
    If the water temperature is difficult to estimate, use the intelligent tester and enter the following menus: Powertrain / Engine / Data List / Coolant Temp and Fuel Temperature.

  12. Initialization is complete.