2014 Hilux · Service Manual ENGINE

INSTALLATION

Removal / installation · Vehicles built from Aug 2013

Versions by build date: Jun 2011 – Jul 2012 Aug 2012 – Jul 2013 from Aug 2013


1. INSTALL GENERATOR ASSEMBLY

A194920
  1. Install the generator with the 2 bolts.

    Torque:
    43 N*m{ 438 kgf*cm , 32 ft.*lbf }

  1. Install the generator wire with the nut and 2 bolts.

    Torque:
    9.8 N*m{ 100 kgf*cm , 87 in.*lbf } for nut
    12.5 N*m{ 127 kgf*cm , 9 ft.*lbf } for bolt

  1. Install the terminal cap.

  1. Connect the generator connector.


2. INSTALL DRIVE BELT

A076442E01
  1. While turning the belt tensioner counterclockwise, align its holes, and then insert a bar of 6 mm (0.24 in.) into the holes to fix the belt tensioner.

  1. Install the V-ribbed belt.

  1. While turning the belt tensioner counterclockwise, remove the bar.

  1. A113028E02
    If it is hard to install the V-ribbed belt, perform the following procedure.

    1. Put the V-ribbed belt on everything except the P/S pump as shown in the illustration.

    2. While releasing the belt tension by turning the belt tensioner counterclockwise, put the V-ribbed belt on the P/S pump.


3. INSTALL V-BANK COVER

A076442E01
  1. While turning the belt tensioner counterclockwise, align its holes, and then insert a bar of 6 mm (0.24 in.) into the holes to fix the belt tensioner.

  1. Install the V-ribbed belt.

  1. While turning the belt tensioner counterclockwise, remove the bar.

  1. A113028E02
    If it is hard to install the V-ribbed belt, perform the following procedure.

    1. Put the V-ribbed belt on everything except the P/S pump as shown in the illustration.

    2. While releasing the belt tension by turning the belt tensioner counterclockwise, put the V-ribbed belt on the P/S pump.


4. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

5. PERFORM INITIALIZATION
  1. Perform initialization (Click here).

    NOTICE:
    Certain systems need to be initialized after disconnecting and reconnecting the cable from the negative (-) battery terminal.

← INSTALLATION (Aug 2012 – Jul 2013)PRECAUTION (from Jun 2011) →