PROPELLER SHAFT ASSEMBLY (except DANA Made) > REASSEMBLY |
| 1. INSTALL UNIVERSAL JOINT SPIDER ASSEMBLY |
![]() |
Apply MP grease to a new 4 spider and bearings.
Fit the spider into the yoke.
![]() |
Using SST, install 2 spider bearings to the spider.
![]() |
Using SST, adjust the spider bearings so that: 1) the yoke does not overlap the snap ring grooves of the spider bearings, and the grooves are as wide as possible; and 2) the groove width on both sides is the same.
Install 2 new snap rings to the installed spider bearings. The snap rings must have an equal thickness which will allow 0 to 0.05 mm (0 to 0.0197 in.) axial play.
| Thickness | Mark |
| 2.19 mm (0.0862 in.) | F |
| 2.21 mm (0.0870 in.) | G |
| 2.23 mm (0.0877 in.) | H |
| 2.25 mm (0.0885 in.) | J |
| 2.27 mm (0.0893 in.) | K |
| 2.29 mm (0.0901 in.) | 1 |
| 2.31 mm (0.0909 in.) | 2 |
| 2.33 mm (0.0917 in.) | 3 |
| 2.35 mm (0.0925 in.) | 4 |
| 2.37 mm (0.0933 in.) | 5 |
| 2.39 mm (0.0940 in.) | 6 |
| 2.41 mm (0.0948 in.) | 7 |
| 2.43 mm (0.0956 in.) | 8 |
| 2.45 mm (0.0964 in.) | N |
| 2.47 mm (0.0972 in.) | 10 |
| 2.49 mm (0.0980 in.) | A |
| 2.51 mm (0.0988 in.) | B |
| 2.53 mm (0.0996 in.) | C |
| 2.55 mm (0.1003 in.) | D |
| 2.57 mm (0.1011 in.) | E |
![]() |
Using a hammer, tap the yoke until there is no clearance between the spider bearings and snap rings.
Align the matchmarks on the yoke and shaft.
Install 2 spider bearings on the shaft yoke.
Install the other universal joint spider(s) using the same procedures.
| 2. INSPECT UNIVERSAL JOINT SPIDER ASSEMBLY |
Check the spider bearings for wear or damage.
If any of the bearings is worn or damaged, replace it.
Check each spider bearing's axial play by turning the yoke while holding the shaft tightly.
| 3. INSPECT PROPELLER WITH CENTER BEARING SHAFT ASSEMBLY |
When the spider bearing is replaced, be sure that the grease fitting holes are facing the direction shown in the illustration.