2013-2015 Land Cruiser Prado · Service Manual Engine / Hybrid System

INSTALLATION

Removal / installation · Vehicles built from Aug 2013


1. INSTALL NO. 2 EMISSION CONTROL VALVE SET
  1. Install the No. 2 emission control valve set with the 3 nuts.

    Torque:
    21 N*m{ 214 kgf*cm , 15 ft.*lbf }

  1. A224703E01
    Align the paint mark with the projection and connect the No. 1 air hose.
    Text in Illustration 
    *1
    Paint Mark
    *2
    Rib
    *a
    Upper
    *b
    LH Side

    HINT:
    Make sure the direction of the hose clamp is as shown in the illustration.

  1. Connect the No. 2 emission control valve set connector.


2. INSTALL NO. 2 AIR TUBE

  1. A226792E01
    Install 2 new gaskets to the No. 2 air tube.
    Text in Illustration 
    *1
    New Gasket
    *2
    No. 2 Air Tube

  1. Install the No. 2 air tube with the 2 bolts and 2 nuts.

    Torque:
    10 N*m{ 102 kgf*cm , 7 ft.*lbf }


3. INSTALL PURGE VSV
  1. Install the purge VSV (Click here).