INSTALLATION
Removal / installation · Vehicles built Sep 2011 – Dec 2011
| 1. INSTALL KNOCK SENSOR |
Install the 2 sensors with the 2 nuts as shown in the illustration.

- Torque:
- 20 N*m{ 204 kgf*cm , 15 ft.*lbf }
Connect the 2 sensor connectors.
| 2. INSTALL AIR PUMP WITH BRACKET AND AIR SWITCHING VALVE |
Install the air pump with bracket with the 2 bolts and 2 nuts in the order shown in the illustration.

- Torque:
- 16 N*m{ 163 kgf*cm , 12 ft.*lbf }
Connect the pressure sensor connector.
Connect the air switching valve connector.
| 3. INSTALL NO. 2 AIR INJECTION SYSTEM HOSE |
Install the hose.

| 4. INSTALL WATER BY-PASS PIPE SUB-ASSEMBLY |
Apply soapy water to the O-ring.
Install a new O-ring to the water by-pass pipe.
Push in the water by-pass pipe.

Install the water by-pass pipe with the bolt.
- Torque:
- 18 N*m{ 184 kgf*cm , 13 ft.*lbf }
Connect the 2 vacuum switching valve hoses to the water by-pass pipe clamp.
Connect the wire harness clamp.
Connect the connector.
| 5. INSTALL INTAKE MANIFOLD |
Install the intake manifold (Click here).
| 6. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL |
- NOTICE:
- When disconnecting the cable, some systems need to be initialized after the cable is reconnected (Click here).
| 7. INSPECT FOR FUEL LEAK |
Connect the intelligent tester to the DLC3.
Turn the engine switch on (IG) and intelligent tester ON.
- NOTICE:
- Do not start the engine.
Enter the following menus: Powertrain / Engine and ECT / Active Test / Activate the Fuel Pump Speed Control.
Check that there are no fuel leaks after doing maintenance anywhere on the fuel system.