2011-2013 Land Cruiser · Service Manual Engine / Hybrid / EV System

INSTALLATION

Removal / installation · Vehicles built from Jan 2012


1. INSTALL AIR SWITCHING VALVE ASSEMBLY

  1. A266181E01
    Install a new gasket and the air switching valve with the 3 bolts.

    Torque:
    24 N*m{ 245 kgf*cm , 18 ft.*lbf }

    Text in Illustration 
    *1
    No. 4 Air Tube
    *2
    Claw
    *3
    Air Switching Valve

    NOTICE:
    Make sure the gasket's claws are not caught between the air switching valve and No. 4 air tube.

  1. Install the 2 bolts.

    Torque:
    10 N*m{ 102 kgf*cm , 7 ft.*lbf }

  1. Connect the wire harness clamp bracket with the bolt.

    Torque:
    8.0 N*m{ 82 kgf*cm , 71 in.*lbf }


2. CONNECT NO. 2 AIR INJECTION SYSTEM HOSE

  1. A266182E01
    Connect the No. 2 air injection system hose.
    Text in Illustration 
    *1
    Protrusion
    *2
    Paint Mark

    HINT:
    Make sure the direction of the hose clamp is as shown in the illustration.

  1. Connect the connector.


3. INSTALL V-BANK COVER SUB-ASSEMBLY

  1. A274416E01
    Attach the 2 V-bank cover hooks to the bracket. Then align the 3 V-bank cover grommets with the 3 pins, and press down on the V-bank cover to attach the pins.
    Text in Illustration 
    *1
    Grommet
    *2
    Pin
    *3
    Hook
    *4
    Bracket

← INSPECTION (from Jan 2012)COMPONENTS (from Jan 2012) →