CANISTER > INSPECTION |
| 1. INSPECT CHARCOAL CANISTER ASSEMBLY |
Visually check the charcoal canister assembly.
![]() |
Visually check the charcoal canister assembly for cracks or damage.
If cracks or damage are found, replace the charcoal canister assembly.
Check canister operation.
![]() |
With port C closed, blow 5 kPa (0.1 kgf/cm2, 0.7 psi) of air into port A, and check that air flows from port B.
| *a | Air |
![]() |
With port A closed, blow 5 kPa (0.1 kgf/cm2, 0.7 psi) of air into port B, and check that air flows from port C.
| *a | Air |
Check for air leaks.
![]() |
Connect a pressure gauge to port A of the charcoal canister assembly.
| *1 | Pressure Gauge |
With port C and port B closed, apply 20 kPa (150 mmHg, 5.91 in.Hg) of pressurized air into port A, then confirm that pressure is retained for 1 minute.
If the result is not as specified, replace the charcoal canister assembly.
| 2. INSPECT NO. 1 CHARCOAL CANISTER FILTER |
Visually check the No. 1 charcoal canister filter.
![]() |
Visually check the No. 1 charcoal canister filter for cracks or damage.
If cracks or damage are found, replace the charcoal canister with bracket assembly.
Check canister operation.
![]() |
Blow 0.5 kPa (0.005 kgf/cm2, 0.1 psi) of air into port A, and check that air flows from port B.
| *a | Air |
Check for air leaks.
![]() |
Connect a pressure gauge to port A of the No. 1 charcoal canister filter.
| *1 | Pressure Gauge |
With port B closed, apply 20 kPa (150 mmHg, 5.91 in.Hg) of pressurized air into port A, then confirm that pressure is retained for 1 minute.
If the result is not as specified, replace the No. 1 charcoal canister filter.
Check the charcoal canister leak detection pump sub-assembly.
![]() |
Connect a positive (+) lead from the auxiliary battery to terminal 5 and a negative (-) lead to terminal 1.
Check that a clicking sound is heard from the leak detection pump.
If the result is not as specified, replace the charcoal canister leak detection pump sub-assembly.