Home › Engine / Hybrid System › 2ZR-FXE STARTING › POWER SWITCH

POWER SWITCH > INSTALLATION

for Preparation Click here



1. INSTALL POWER SWITCH


    A216893
  1. Attach the 2 claws to install the power switch.



2. INSTALL UPPER INSTRUMENT PANEL FINISH PANEL SUB-ASSEMBLY


    B223459
  1. Connect the connector.

  1. Engage the 3 claws to install the upper instrument panel finish panel sub-assembly.



3. INSTALL INSTRUMENT CLUSTER FINISH PANEL GARNISH
  1. Connect the connector.

  1. Engage the 14 claws to install the instrument cluster finish panel garnish.



4. INSTALL LOWER CENTER INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY


    B223456
  1. Engage the 7 claws and 2 clips to install the lower center instrument cluster finish panel sub-assembly.



5. INSTALL INTEGRATION CONTROL AND PANEL ASSEMBLY


    B223453
  1. Connect each connector.

  1. Engage the 6 claws to install the integration control and panel assembly.



6. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

NOTICE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected (Click here).



7. INSTALL REAR NO. 3 FLOOR BOARD


    B227791
  1. Engage the 2 guides to install the rear No. 3 floor board.



8. INSTALL REAR DECK FLOOR BOX
  1. Install the rear deck floor box.



9. INSTALL REAR NO. 2 FLOOR BOARD


    B227788E01
  1. Engage the 3 guides <A>.

  1. Engage the 2 guides <B> and install the rear No. 2 floor board as shown in the illustration.