Home › Vehicle Exterior › EXTERIOR PANELS / TRIM › ROOF DRIP SIDE FINISH MOULDING

ROOF DRIP SIDE FINISH MOULDING > INSTALLATION

for Preparation Click here



1. INSTALL ROOF DRIP SIDE FINISH MOULDING CLIP (w/o Sliding Roof)

NOTICE:
  1. If reusing the clips, do not remove the double-sided tape remaining on the clips and where the clips will be installed on the body.
  2. If installing new clips, remove the double-sided tape remaining where the clips will be installed on the body and clean the body with a non-residue solvent.



    B229383E01
  1. Apply a 2 to 3 mm (0.0787 to 0.118 in.) bead of adhesive (3M DP-105 or equivalent) to new roof drip side finish moulding clips.

    HINT:
    Adhesive strength (tensile strength): 13.7 MPa (140 kgf/cm2, 1987 psi) or more (when the temperature is 23°C (73°F).)

  1. Press and install the 2 roof drip side finish moulding clips.



  1. Install the clips to the positions on the roof panel shown in the illustration. Determine the locations and firmly press and install the 2 roof drip side finish moulding clips after lightly applying adhesive (3M DP-105 or equivalent).


    B229384E01


    Text in Illustration 
    *1
    Protruding Part
    -
    -
    Standard Dimension 
    Installation Area
    Dimension
    Measurement
    for Front Side
    A
    4.0 mm (0.158 in.)
    B
    2.7mm (0.106 in.)
    for Rear Side
    C
    4.3 mm (0.169 in.)
    D
    3.9 mm (0.154 in.)

  1. Install the roof drip center side finish moulding when 20 minutes or more have elapsed after pressing and installing the 2 roof drip side finish moulding clips.

    HINT:
    1. Initial hardening time: 20 minutes
    2. Complete hardening time: 48 hours



2. INSTALL ROOF DRIP CENTER SIDE FINISH MOULDING (w/o Sliding Roof)


    B229381
  1. Engage the 2 clips and install the roof drip center side finish moulding as shown in the illustration.



3. INSTALL ROOF DRIP SIDE FINISH MOULDING CLIP (w/ Sliding Roof)

NOTICE:
  1. If reusing the clips, do not remove the double-sided tape remaining on the clips and where the clips will be installed on the body.
  2. If installing new clips, remove the double-sided tape remaining where the clips will be installed on the body and clean the body with a non-residue solvent.



    B229383E01
  1. Apply a 2 to 3 mm (0.0787 to 0.118 in.) bead of adhesive (3M DP-105 or equivalent) to new roof drip side finish moulding clips.

    HINT:
    Adhesive strength (tensile strength): 13.7 MPa (140 kgf/cm2, 1987 psi) or more (when the temperature is 23°C (73°F).)

  1. Press and install the 2 roof drip side finish moulding clips.



  1. Install the clips to the positions on the roof panel shown in the illustration. Determine the locations and firmly press and install the 2 roof drip side finish moulding clips after lightly applying adhesive (3M DP-105 or equivalent).


    B229385E01


    Text in Illustration 
    *1
    Protruding Part
    -
    -
    Standard Dimension 
    Installation Area
    Dimension
    Measurement
    for Front Side
    A
    2.8 mm (0.150 in.)
    B
    3.7mm (0.146 in.)
    for Rear Side
    C
    4.3 mm (0.169 in.)
    D
    3.9 mm (0.154 in.)

  1. Install the roof drip center side finish moulding when 20 minutes or more have elapsed after pressing and installing the 2 roof drip side finish moulding clips.

    HINT:
    1. Initial hardening time: 20 minutes
    2. Complete hardening time: 48 hours



4. INSTALL ROOF DRIP CENTER SIDE FINISH MOULDING (w/ Sliding Roof)


    B229382
  1. Engage the 2 clips and install the roof drip center side finish moulding as shown in the illustration.