PURGE VALVE > INSPECTION

for Preparation Click here



1. INSPECT NO. 1 VACUUM SWITCHING VALVE ASSEMBLY


A148341E04
  1. Measure the resistance according to the value(s) in the table below.

    Standard Resistance:
    Tester Connection
    Condition
    Specified Condition
    1 - 2
    20°C (68°F)
    23 to 26 Ω
    1 - VSV body ground
    Always
    10 kΩ or higher
    2 - VSV body ground
    10 kΩ or higher

    If the result is not as specified, replace the No. 1 vacuum switching valve assembly.



    A148342E03
  1. Inspect the No. 1 vacuum switching valve assembly operation.

    1. Check that air does not flow from ports.



    2. A148343E01
    3. Apply battery voltage across the terminals.

    4. Check that air flows from ports.
      If operation is not as specified, replace the No. 1 vacuum switching valve assembly.