Home › Engine / Hybrid System ยท 2UZ-FE › INTAKE / EXHAUST › EXHAUST MANIFOLD

EXHAUST MANIFOLD > INSTALLATION

for Preparation Click here



1. INSTALL EXHAUST MANIFOLD SUB-ASSEMBLY LH


    A156200E02
  1. Place a new gasket on the cylinder head with the "L" mark facing the manifold side.

    NOTICE:
    Be careful of the installation direction.



    A156204E03
  1. Temporarily install the exhaust manifold sub-assembly LH, and then uniformly tighten 8 new nuts in several steps, in the sequence shown in the illustration.

    Torque:
    44 N*m{ 449 kgf*cm , 32 ft.*lbf }



2. INSTALL NO. 2 EXHAUST MANIFOLD HEAT INSULATOR
  1. Temporarily install the No. 2 exhaust manifold heat insulator with the 4 bolts.



    A156202E03
  1. Uniformly tighten the 4 bolts in several steps, in the sequence shown in the illustration.

    Torque:
    7.5 N*m{ 76 kgf*cm , 66 in.*lbf }



3. INSTALL NO. 2 STEERING INTERMEDIATE SHAFT SUB-ASSEMBLY


C155151E01
  1. Align the matchmarks on the No. 2 steering intermediate shaft and power steering gear.

  1. Install the bolt.

    Torque:
    35 N*m{ 360 kgf*cm , 26 ft.*lbf }



4. INSTALL EXHAUST MANIFOLD SUB-ASSEMBLY RH


    A156199E03
  1. Place a new gasket on the cylinder head with the "R" mark facing the manifold side.

    NOTICE:
    Be careful of the installation direction.



    A156203E02
  1. Temporarily install the exhaust manifold sub-assembly RH, and then uniformly tighten 8 new nuts in several steps, in the sequence shown in the illustration.

    Torque:
    44 N*m{ 449 kgf*cm , 32 ft.*lbf }



5. INSTALL NO. 1 EXHAUST MANIFOLD HEAT INSULATOR
  1. Temporarily install the No. 1 exhaust manifold heat insulator with the 4 bolts.



    A156201E01
  1. Uniformly tighten the 4 bolts in several steps, in the sequence shown in the illustration.

    Torque:
    7.5 N*m{ 76 kgf*cm , 66 in.*lbf }



6. INSTALL FRONT NO. 2 EXHAUST PIPE ASSEMBLY


    A185632
  1. Install a new gasket and the front No. 2 exhaust pipe assembly to the exhaust manifold LH with 3 new nuts.

    Torque:
    54 N*m{ 551 kgf*cm , 40 ft.*lbf }

  1. Install a new gasket and the front No. 2 exhaust pipe assembly to the front No. 3 exhaust pipe sub-assembly with the 2 bolts and 2 nuts.

    Torque:
    48 N*m{ 489 kgf*cm , 35 ft.*lbf }

  1. Connect the air fuel ratio sensor connector.

  1. Connect the heated oxygen sensor connector.



7. INSTALL FRONT PROPELLER SHAFT ASSEMBLY (for 4WD)


    C179230E02
  1. Align the matchmarks on the differential and propeller shaft flange.

  1. Align the matchmarks on the transfer and propeller shaft flange.

  1. Install the front propeller shaft assembly with the 8 nuts and 8 washers.

    Torque:
    80 N*m{ 816 kgf*cm , 59 ft.*lbf }



8. INSTALL PROPELLER SHAFT HEAT INSULATOR (for 4WD)


C158452
  1. Install the heat insulator to the heat insulator bracket with the 2 bolts.

    Torque:
    16 N*m{ 163 kgf*cm , 12 ft.*lbf }



9. INSTALL FRONT EXHAUST PIPE ASSEMBLY


    A185633
  1. Install a new gasket and the front exhaust pipe assembly to the exhaust manifold RH with 3 new nuts.

    Torque:
    54 N*m{ 551 kgf*cm , 40 ft.*lbf }

  1. Install a new gasket and the front exhaust pipe assembly to the center exhaust pipe assembly with the 2 bolts.

    Torque:
    48 N*m{ 489 kgf*cm , 35 ft.*lbf }

  1. Connect the air fuel ratio sensor connector.

  1. Connect the heated oxygen sensor connector and 2 clamps.



10. INSTALL AIR SWITCHING VALVE ASSEMBLY (for Bank 2)


    A153513E01
  1. Install the air switching valve assembly with the 3 nuts.

    Torque:
    16 N*m{ 163 kgf*cm , 12 ft.*lbf }

    NOTICE:
    Do not hold the bracket of the air switching valve assembly.



11. INSTALL NO. 2 AIR TUBE (for Bank 2)


    A153512
  1. Temporarily install a new gasket and the No. 2 air tube to the exhaust manifold side with the 2 nuts.

  1. Install a new gasket and the No. 2 air tube to the air switching valve side with the 2 nuts.

    Torque:
    10 N*m{ 102 kgf*cm , 7 ft.*lbf }

  1. Tighten the 2 nuts on the exhaust manifold side.

    Torque:
    10 N*m{ 102 kgf*cm , 7 ft.*lbf }



    A153510
  1. Connect the air switching valve assembly connector.

  1. Connect the wire harness clamp.



12. CONNECT NO. 2 AIR INJECTION SYSTEM HOSE
  1. Connect the No. 2 air injection system hose to the air switching valve assembly.



13. INSTALL WATER BY-PASS PIPE ASSEMBLY


    A156198E01
  1. Connect the 2 water hoses to the transmission oil cooler.

  1. Install the water by-pass pipe assembly with the 3 bolts.

    Torque:
    18 N*m{ 184 kgf*cm , 13 ft.*lbf }



14. CONNECT NO. 5 WATER BY-PASS HOSE


    A156193
  1. Connect the No. 5 water by-pass hose with the clip.



15. INSTALL HEATER OUTLET WATER HOSE


A156187


16. INSTALL ENGINE OIL LEVEL DIPSTICK GUIDE


    A150112E02
  1. Apply a light coat of engine oil to a new O-ring.

  1. Install a new O-ring to the guide.

  1. Install the dipstick guide with the bolt.

    Torque:
    8.0 N*m{ 82 kgf*cm , 71 in.*lbf }

  1. Install the dipstick.



17. INSTALL AIR SWITCHING VALVE ASSEMBLY (for Bank 1)


A153519E01
  1. Install the air switching valve assembly with the 3 nuts.

    Torque:
    16 N*m{ 163 kgf*cm , 12 ft.*lbf }

    NOTICE:
    Do not hold the bracket of the air switching valve assembly.



18. INSTALL NO. 3 AIR TUBE (for Bank 1)


A153518
  1. Temporarily install a new gasket and the No. 3 air tube to the exhaust manifold side with the 2 nuts.

  1. Install a new gasket and the No. 3 air tube to the air switching valve side with the 2 nuts.

    Torque:
    10 N*m{ 102 kgf*cm , 7 ft.*lbf }

  1. Tighten the 2 nuts on the exhaust manifold side.

    Torque:
    10 N*m{ 102 kgf*cm , 7 ft.*lbf }



19. INSTALL NO. 2 AIR HOSE (for Bank 1)


    A153516
  1. Install the No. 2 air hose.



    A153515
  1. Connect the air switching valve assembly connector.

  1. Connect the fuel hose clamp.



20. INSTALL AIR CLEANER ASSEMBLY


A185616
  1. Install the air cleaner assembly with the 2 bolts.

    Torque:
    5.0 N*m{ 51 kgf*cm , 44 in.*lbf }

  1. Connect the mass air flow meter connector and clamp.



21. INSTALL AIR CLEANER HOSE ASSEMBLY


    A153488E02
  1. Install the air cleaner hose assembly with the 2 clamps.

    Torque:
    4.0 N*m{ 41 kgf*cm , 35 in.*lbf }

    HINT:
    Make sure that the clamp band end is aligned with the limit mark when the hose clamp is tightened, as indicated by A and B in the illustration.

  1. Connect the vacuum hose and No. 2 ventilation hose.



22. ADD ENGINE COOLANT
  1. Add engine coolant.

    Standard capacity:
    9.7 liters (10.3 US qts, 8.5 Imp. qts)

    HINT:
    1. TOYOTA vehicles are filled with TOYOTA SLLC at the factory. In order to avoid damage to the engine cooling system and other technical problems, only use TOYOTA SLLC or similar high quality ethylene glycol based non-silicate, non-amine, non-nitrite, non-borate coolant with long-life hybrid organic acid technology (coolant with long-life hybrid organic acid technology is a combination of low phosphates and organic acids).
    2. The thermostat opening timing can be confirmed by pressing the inlet radiator hose by hand, and checking when the engine coolant starts to flow inside the hose.



    A151850E03
  1. Slowly pour coolant into the radiator reservoir until it reaches the FULL line.

  1. Install the reservoir cap.

  1. Press the inlet and outlet radiator hoses several times by hand, and then check the coolant level. If the coolant level is low, add coolant.

  1. Install the radiator cap.

  1. Start the engine and warm it up until the thermostat opens.

    HINT:
    The thermostat opening timing can be confirmed by pressing the inlet radiator hose by hand, and checking when the engine coolant starts to flow inside the hose.

  1. Maintain the engine speed at 2000 to 2500 rpm and warm up the engine until the cooling fan operates.

    NOTICE:
    1. Make sure that the radiator reservoir still has some coolant in it.
    2. Pay attention to the needle of the water temperature meter. Make sure that the needle does not show an abnormally high temperature.
    3. If there is not enough coolant, the engine may burn out or overheat.

  1. Press the inlet and outlet radiator hoses several times by hand to bleed air.

    CAUTION:
    1. Wear protective gloves.
    2. Be careful as the radiator hoses are hot.
    3. Keep your hands away from the fan.

  1. Stop the engine, and wait until the engine coolant cools down.



    A151850E04
  1. If the coolant level is below the LOW line, repeat all of the procedures above.



23. INSPECT FOR COOLANT LEAK

CAUTION:
Do not remove the radiator cap while the engine and radiator are still hot. Pressurized, hot engine coolant and steam may be released and cause serious burns.



    A162054
  1. Fill the radiator with coolant and attach a radiator cap tester.

  1. Warm up the engine.

  1. Using the radiator cap tester, increase the pressure inside the radiator to 118 kPa (1.2 kgf/cm2, 17 psi), and check that the pressure does not drop. If the pressure drops, check the hoses, radiator and water pump for leaks. If no external leaks are found, check the heater core, cylinder block and head.



24. INSTALL THROTTLE BODY COVER SUB-ASSEMBLY


    A153486
  1. Install the throttle body cover sub-assembly with the 2 nuts.

    Torque:
    7.5 N*m{ 76 kgf*cm , 66 in.*lbf }



25. INSTALL NO. 1 ENGINE UNDER COVER


    A150108
  1. Hook the engine under cover onto the vehicle body as shown in the illustration.

  1. Install the 3 screws and 5 bolts.

    1. for bolt

    Torque:
    29 N*m{ 296 kgf*cm , 21 ft.*lbf }

    1. for screw

    Torque:
    3.0 N*m{ 31 kgf*cm , 27 in.*lbf }



26. INSPECT FOR EXHAUST GAS LEAK


27. INSTALL FRONT FENDER APRON SEAL LH
  1. Install the front fender apron seal LH with the 6 clips.



28. INSTALL FRONT FENDER APRON SEAL REAR LH
  1. Install the front fender apron seal rear LH with the 5 clips.



29. INSTALL FRONT FENDER APRON SEAL RH
  1. Install the front fender apron seal RH with the 6 clips.



30. INSTALL FRONT FENDER APRON SEAL REAR RH
  1. Install the front fender apron seal rear RH with the 5 clips.