Home › Engine / Hybrid System › 3UR-FE ENGINE MECHANICAL › ENGINE UNIT

ENGINE UNIT > INSTALLATION

for Preparation Click here



1. INSTALL SPARK PLUG


2. INSTALL IGNITION COIL ASSEMBLY
  1. Install the 8 ignition coils with the 8 bolts.

    Torque:
    10 N*m{ 102 kgf*cm , 7 ft.*lbf }



    A151832
  1. Connect the 8 ignition coil connectors.



3. INSTALL KNOCK SENSOR


    A184969E03
  1. Install the 4 knock sensor with the 4 bolts so that the knock sensors are angled as shown in the illustration.

    Torque:
    20 N*m{ 204 kgf*cm , 15 ft.*lbf }

    Text in Illustration 
    *a
    Bank 2 Sensor 1
    *b
    Bank 1 Sensor 1
    *c
    Bank 2 Sensor 2
    *d
    Bank 1 Sensor 2
    *e
    Front
    *f
    Upper
    *g
    Rear

    NOTICE:
    The acceptable installation angle of the knock sensor is between 10° upward and 2° downward from the horizontal position.

  1. Connect the 4 knock sensor connectors.



4. INSTALL CASE SEPARATOR
  1. Install the case separator with the 4 bolts.

    Torque:
    10 N*m{ 102 kgf*cm , 7 ft.*lbf }



    A309115E01
  1. Install the No. 9 water by-pass hose and No. 10 water by-pass hose to the case separator, and slide the 2 clamps to secure the hoses.

    HINT:
    Make sure that the color on the hose matches the color on the case separator.



5. INSTALL ENGINE WIRE
  1. Install the engine wire, and then attach the 3 clamps.

  1. Connect the 4 knock sensor connectors.



6. INSTALL INLET WATER HOUSING


    A162555E01
  1. Install a new gasket to the water pump.



    A183227E01
  1. Connect the No. 3 water by-pass hose to the inlet water housing.

  1. Install the inlet water housing with the 3 bolts.

    Torque:
    21 N*m{ 214 kgf*cm , 16 ft.*lbf }

    HINT:
    Install the hose so that the direction of the hose clamp is as indicated in the illustration.



7. INSTALL OIL PRESSURE SENDER GAUGE ASSEMBLY


    A118764E02
  1. Apply adhesive to 2 or 3 threads of the oil pressure sender gauge.

    Adhesive:
    Toyota Genuine Adhesive 1344, Three Bond 1344 or equivalent



    A162467
  1. Install the oil pressure sender gauge.

    Torque:
    15 N*m{ 153 kgf*cm , 11 ft.*lbf }

    NOTICE:
    Do not start the engine within 1 hour after installation.



    A163657
  1. Connect the sender gauge connector.



8. INSTALL NO. 1 IDLER PULLEY SUB-ASSEMBLY
  1. Install the No. 1 idler pulley sub-assembly with the bolt.

    Torque:
    43 N*m{ 438 kgf*cm , 32 ft.*lbf }



9. INSTALL WATER PUMP PULLEY


    A151837E02
  1. Temporarily install the pulley with the 4 bolts.

  1. Using SST, hold the pulley and tighten the 4 bolts.

    SST
    09960-10010   (09962-01000, 09963-01000)

    Torque:
    21 N*m{ 214 kgf*cm , 16 ft.*lbf }



10. INSTALL WATER BY-PASS PIPE SUB-ASSEMBLY
  1. Connect the No. 2 water by-pass hose and No. 3 water by-pass hose to the water by-pass pipe sub-assembly, and slide the 2 clamps to secure the hoses.

  1. Install the water by-pass pipe sub-assembly with the 2 bolts.

    Torque:
    10 N*m{ 102 kgf*cm , 7 ft.*lbf }



11. INSTALL NO. 1 ENGINE COVER


A158656

NOTICE:
Make sure that the No. 1 engine cover is level with the top surface of the intake port of the cylinder head for 1 and 2.

  1. Install the No. 1 engine cover.

    HINT:
    1. Align the No. 1 engine cover cutouts with the air tube.
    2. Align the No. 1 engine cover with the electric air control valve surface and cylinder head wall.



12. INSTALL NO. 2 CYLINDER HEAD COVER


A158538

NOTICE:
Make sure that the No. 2 cylinder head cover is level with the top surface of the intake port of the cylinder head.

  1. Install the No. 2 cylinder head cover.

    HINT:
    1. Align the No. 2 cylinder head cover cutout with the air tube.
    2. Align the No. 2 cylinder head cover with the front water by-pass joint and cylinder head wall.



13. INSTALL FRONT WATER BY-PASS JOINT
  1. Install 2 new gaskets and the front water by-pass joint with the 4 nuts to the cylinder head.

    Torque:
    21 N*m{ 214 kgf*cm , 16 ft.*lbf }

  1. Connect the No. 2 water by-pass hose to the front water by-pass joint, and slide the clamp to secure the hose.



14. INSTALL NO. 1 WATER BY-PASS HOSE
  1. Connect the No. 1 water by-pass hose to the inlet water housing and front water by-pass joint, and slide the 2 clamps to secure the hoses.



15. INSTALL WATER BY-PASS PIPE HOSE


    A165547
  1. Connect the 4 hoses.

  1. Install the water by-pass pipe with the 3 bolts.

    Torque:
    10 N*m{ 102 kgf*cm , 7 ft.*lbf }



16. INSTALL FUEL TUBE SUB-ASSEMBLY
  1. Install the fuel tube sub-assembly.



17. INSTALL NO. 2 FUEL TUBE SUB-ASSEMBLY
  1. Install the No. 2 fuel tube sub-assembly with the 2 bolts.

    Torque:
    10 N*m{ 102 kgf*cm , 7 ft.*lbf }



18. INSTALL INTAKE MANIFOLD


    A162094
  1. Place 2 new gaskets on the intake manifold.

  1. Place the intake manifold on the cylinder head sub-assembly.

  1. Install and uniformly tighten the 8 bolts and 2 nuts in several steps.

    Torque:
    21 N*m{ 214 kgf*cm , 15 ft.*lbf }

  1. Install the wire harness clamp bracket with the bolt.

    Torque:
    8.0 N*m{ 82 kgf*cm , 71 in.*lbf }

  1. Attach the 3 wire harness clamps to the 3 wire harness clamp brackets.

  1. Install the No. 1 tube with the 2 bolts.

    Torque:
    8.2 N*m{ 84 kgf*cm , 73 in.*lbf }

  1. Connect the union to connector tube hose to the No. 1 tube, and slide the clamp to secure the hose.

  1. Connect the purge line hose to the purge VSV, and slide the clamp to secure the hose.

  1. Connect the 2 vacuum switching valve connectors.

  1. Connect the ventilation hose to the intake manifold, and slide the clamp to secure the hose.

  1. Connect the 2 water by-pass hoses to the inlet water housing and front water by-pass joint, and slide the 2 clamps to secure the hoses.

  1. Connect the throttle body connector to the throttle body assembly.



19. INSTALL NO. 1 HOSE TO HOSE TUBE
  1. Install the No. 1 hose to hose tube with the 2 bolts.

    Torque:
    8.2 N*m{ 84 kgf*cm , 73 in.*lbf }



20. INSTALL VENTILATION HOSE ASSEMBLY


    A163820E03
  1. Install the ventilation hose assembly with the 2 bolts.

    Torque:
    for bolt A:
    21 N*m{ 214 kgf*cm , 15 ft.*lbf }
    for bolt B:
    10 N*m{ 102 kgf*cm , 7 ft.*lbf }



21. INSTALL NO. 2 FUEL DELIVERY PIPE SUB-ASSEMBLY


    A256331
  1. Install the 2 spacers and 4 insulators to the cylinder head LH.

  1. Install the fuel delivery pipe (with injectors) to the cylinder head LH.



  1. Install the 2 bolts.

    Torque:
    21 N*m{ 214 kgf*cm , 16 ft.*lbf }


    NOTICE:
    A163659E01
    Make sure that the part of the injector labeled B is between the parts of the fuel delivery pipe labeled A.

  1. Connect the No. 7 wire harness connector.



22. INSTALL FUEL DELIVERY PIPE SUB-ASSEMBLY


    A256330
  1. Install the 2 spacers and 4 insulators to the cylinder head RH.

  1. Install the fuel delivery pipe (with injectors) to the cylinder head RH.



  1. Install the 2 bolts.

    Torque:
    21 N*m{ 214 kgf*cm , 16 ft.*lbf }


    NOTICE:
    A163659E01
    Make sure that the part of the injector labeled B is between the parts of the fuel delivery pipe labeled A.



23. CONNECT FUEL TUBE SUB-ASSEMBLY


    A161415
  1. Connect the fuel tube to the No. 2 fuel delivery pipe (for quick type A) (Click here).



    A256329
  1. Connect the fuel tube to the fuel delivery pipe (for quick type A) (Click here).



24. CONNECT NO. 2 FUEL TUBE SUB-ASSEMBLY


    A161418
  1. Connect the No. 2 fuel tube to the fuel pressure regulator (for quick type A) (Click here).



25. INSTALL NO. 1 ENGINE COVER SUB-ASSEMBLY
  1. Install the No. 1 engine cover sub-assembly.



26. INSTALL NO. 3 ENGINE COVER
  1. Install the No. 3 engine cover.



27. INSTALL FRONT NO. 1 ENGINE MOUNTING BRACKET LH
  1. Install the front No. 1 engine mounting bracket LH with the 4 bolts.

    Torque:
    35 N*m{ 357 kgf*cm , 26 ft.*lbf }



28. INSTALL FRONT NO. 1 ENGINE MOUNTING BRACKET RH
  1. Install the front No. 1 engine mounting bracket RH with the 4 bolts.

    Torque:
    35 N*m{ 357 kgf*cm , 26 ft.*lbf }



29. INSTALL FRONT ENGINE MOUNTING INSULATOR LH
  1. Install the front engine mounting insulator LH with the nut.

    Torque:
    72 N*m{ 734 kgf*cm , 53 ft.*lbf }



30. INSTALL FRONT ENGINE MOUNTING INSULATOR
  1. Install the front engine mounting insulator with the nut.

    Torque:
    72 N*m{ 734 kgf*cm , 53 ft.*lbf }



31. INSTALL CYLINDER BLOCK WATER DRAIN COCK PLUG


    A076531E01
  1. Apply adhesive to 2 or 3 threads of the cylinder block water drain.

    Adhesive:
    Toyota Genuine Adhesive 1344, Three Bond 1344 or equivalent



    A163841E01
  1. Install the 2 cylinder block water drains.

    Torque:
    30 N*m{ 306 kgf*cm , 22 ft.*lbf }

  1. Further tighten the cylinder block water drains within 360° so that the drain cock pipes are within the range shown in the illustration.

    NOTICE:
    1. Do not rotate the cylinder block water drains more than 1 revolution (360°) after tightening the cylinder block water drains to the specified torque.
    2. Do not loosen the cylinder block water drains to adjust them. If an adjustment is necessary, remove the cylinder block water drains and reinstall them.

  1. Install the cylinder block water drain cock plugs to the cylinder block water drains.

    Torque:
    13 N*m{ 133 kgf*cm , 10 ft.*lbf }



32. INSTALL NO. 1 FUEL PIPE SUB-ASSEMBLY
  1. Install the No. 1 fuel pipe sub-assembly (Click here).



33. INSTALL ENGINE WIRE


    A259666E01
  1. Install the engine wire.

  1. Install the 3 bolts as shown in the illustration.

    Torque:
    8.5 N*m{ 87 kgf*cm , 75 in.*lbf }

  1. Attach the 4 clamps.

  1. Attach the 9 clamps.

  1. Connect the oil pressure sender gauge connector.

  1. Connect the throttle sensor connector.

  1. Connect the fuel injector connector.

  1. Connect the 2 VVT sensor connectors.

  1. Connect the 4 ignition coil connectors.

  1. Connect the 2 camshaft timing control valve connectors.

  1. Attach the 8 clamps and install the engine wire with the bolt.

    Torque:
    20 N*m{ 204 kgf*cm , 15 ft.*lbf }

  1. Connect the fuel injector connector.

  1. Connect the engine coolant temperature sensor connector.

  1. Connect the purge VSV connector.

  1. Connect the vacuum switching valve connector (for ACIS).

  1. Connect the camshaft position sensor connector.

  1. Connect the 2 VVT sensor connectors.

  1. Connect the 4 ignition coil connectors.

  1. Connect the 2 camshaft timing control valve connectors.