Home › DRIVE LINE › PROPELLER SHAFT › REAR PROPELLER SHAFT ASSEMBLY (for Access Cab 4WD and Double Cab 4WD)

REAR PROPELLER SHAFT ASSEMBLY (for Access Cab 4WD and Double Cab 4WD) > INSTALLATION

for Preparation Click here



1. INSPECT PROPELLER WITH CENTER BEARING SHAFT ASSEMBLY



F052218E01

HINT:
When replacing the spider bearing, make sure that the grease fitting assembly hole is facing in the direction shown in the illustration.



2. INSTALL PROPELLER WITH CENTER BEARING SHAFT ASSEMBLY


C098709E02
  1. Align the matchmarks on the yoke and transfer flange.

  1. Install the propeller shaft with the 4 nuts and 4 washers.

    Torque:
    88 N*m{ 899 kgf*cm , 65 ft.*lbf }



    C098708E02
  1. Align the matchmarks on the yoke and differential flange.

  1. Install the propeller shaft with the 4 bolts, 4 nuts and 4 washers.

    Torque:
    88 N*m{ 899 kgf*cm , 65 ft.*lbf }



    D033899E01
  1. Provisionally install the center support bearing with 2 mounting bolts.

    HINT:
    Make sure the bearing is installed with the drain hole facing downwards.

  1. Torque the 2 bolts.

    Torque:
    36 N*m{ 369 kgf*cm , 27 ft.*lbf }