CANISTER > INSPECTION |
| 1. INSPECT CANISTER ASSEMBLY |
![]() |
Visually check the canister for cracks or damage.
If cracks or damage are found, replace the canister assembly.
![]() |
Check canister operation.
With the purge port closed, blow 1.67 kPa (0.02 kgf/cm2, 0.24 psi) of air into the vent port, and check that air flows from the air inlet port.
If the result is not as specified, replace the canister assembly.
![]() |
With the vent port closed, blow 1.10 kPa (0.01 kgf/cm2, 0.16 psi) of air inlet port, and check that air flows from the purge port.
If the result is not as specified, replace the canister assembly.
![]() |
Check for air leakage.
Remove the air hose between ports A and B.
Connect a pressure gauge to the vent port of the charcoal canister.
With port B, purge port and the air inlet port closed and port A open, apply 19.6 kPa (0.20 kgf/cm2, 2.81 psi) of pressurized air into the vent port, then confirm that pressure is retained for 1 minute.
If the result is not as specified, replace the canister assembly.
![]() |
Check leak detection pump.
Remove the detection pump from the charcoal canister.
Check that air flows from port A to B and then to C.
If the result is not as specified, replace the canister assembly.
![]() |
Connect the positive (+) lead of the battery to terminal 7 and the negative (-) lead to terminal 6.
Check that the valve is closed.
If the result is not as specified, replace the canister assembly.
Install the detection pump.