Home › Engine / Hybrid System › HYBRID / BATTERY CONTROL › HV RELAY ASSEMBLY
RM3700E _51 Engine / Hybrid System _093506 HYBRID / BATTERY CONTROL _0441196 HV RELAY ASSEMBLY G

HYBRID / BATTERY CONTROL  HV RELAY ASSEMBLY  INSPECTION  


PROCEDURE

Hide G3850 1.INSPECT NO.1 TRACTION BATTERY DEVICE BOX ASSEMBLY (for 2WD)

a.

Inspect SMRB:

i.

Measure the resistance according to the value(s) in the table below.

A413114C23
3.844,1.073 4.208,1.281 0.365,0.208 3.167,0.208 3.552,0.427 0.385,0.219 5.625,0.177 6.042,0.385 0.417,0.208 3.385,1.188 3.094,1.354 true 3.604,1.188 3.844,1.375 true 3.021,0.406 3.354,0.667 true 5.813,0.708 6.313,1.125 true 0.104,0.094 0.417,0.25 0.313,0.156 10 false *a 3.708,1.385 4.135,1.552 0.427,0.167 10 true SMRB 2.927,1.385 3.24,1.552 0.313,0.167 10 true GND 2.646,0.313 2.979,0.479 0.333,0.167 10 true CBI 3.896,1.104 4.208,1.26 0.313,0.156 10 false O70 3.292,0.24 3.542,0.406 0.25,0.167 10 true a1 6.396,1.115 6.573,1.313 0.177,0.198 10 true + 5.698,0.198 6.01,0.354 0.313,0.156 10 true z10
*a Component without harness connected
(No. 1 Traction Battery Device Box Assembly)
- -


Standard Resistance:
Tester Connection Condition Specified Condition

Click Location & Routing(a1,z10)Location & Routing

Click Connector(a1)Body>HV Floor Under Wire>HV Battery Junction Block Assembly

Click Connector(z10)Body>other>HV Supply Battery Assembly , HV Battery Junction Block Assembly

a1-1 (CBI) - z10-1 (+) Auxiliary battery voltage not applied between terminals O70-1 (SMRB) and O70-3 (GND) 10 kΩ or higher
a1-1 (CBI) - z10-1 (+) Auxiliary battery voltage applied between terminals O70-1 (SMRB) and O70-3 (GND) Below 1 Ω



ii.

Measure the resistance according to the value(s) in the table below.

Standard Resistance:
Tester Connection Condition Specified Condition

Click Location & Routing(O70)Location & Routing

Click Connector(O70)Body>Floor Wire>HV Battery Junction Block Assembly

O70-1 (SMRB) - O70-3 (GND) -40 to 80°C (-40 to 176°F) 25.0 to 59.0 Ω


If the result is not as specified, replace the No. 1 traction battery device box assembly.



b.

Inspect SMRG:

i.

Measure the resistance according to the value(s) in the table below.

A413114C24
3.76,1.031 4.115,1.24 0.354,0.208 2.219,0.104 2.583,0.344 0.365,0.24 1.167,0.115 1.531,0.323 0.365,0.208 3.021,1.354 3.292,1.188 true 3.667,1.365 3.417,1.198 true 2.063,1.063 2.396,0.677 true 0.833,0.854 1.344,0.656 true 0.573,0.146 0.885,0.302 0.313,0.156 10 false *a 3.802,1.052 4.26,1.25 0.458,0.198 10 false O70 3.552,1.406 3.885,1.615 0.333,0.208 10 true GND 2.813,1.396 3.271,1.583 0.458,0.188 10 true SMRG 2.281,0.156 2.552,0.313 0.271,0.156 10 true a2 1.229,0.135 1.5,0.302 0.271,0.167 10 true z9 1.813,1 2.188,1.208 0.375,0.208 10 false CEI 0.719,0.781 0.875,0.979 0.156,0.198 10 false -
*a Component without harness connected
(No. 1 Traction Battery Device Box Assembly)
- -


Standard Resistance:
Tester Connection Condition Specified Condition

Click Location & Routing(a2,z9)Location & Routing

Click Connector(a2)Body>HV Floor Under Wire>HV Battery Junction Block Assembly

Click Connector(z9)Body>other>HV Supply Battery Assembly , HV Battery Junction Block Assembly

a2-1 (CEI) - z9-1 (-) Auxiliary battery voltage not applied between terminals O70-4 (SMRG) and O70-3 (GND) 10 kΩ or higher
a2-1 (CEI) - z9-1 (-) Auxiliary battery voltage applied between terminals O70-4 (SMRG) and O70-3 (GND) Below 1 Ω



ii.

Measure the resistance according to the value(s) in the table below.

Standard Resistance:
Tester Connection Condition Specified Condition

Click Location & Routing(O70)Location & Routing

Click Connector(O70)Body>Floor Wire>HV Battery Junction Block Assembly

O70-4 (SMRG) - O70-3 (GND) -40 to 80°C (-40 to 176°F) 25.0 to 59.0 Ω


If the result is not as specified, replace the No. 1 traction battery device box assembly.



c.

Inspect SMRP:

i.

Measure the resistance according to the value(s) in the table below.

A413114C25
3.76,1.031 4.115,1.24 0.354,0.208 2.219,0.104 2.583,0.344 0.365,0.24 1.167,0.115 1.531,0.323 0.365,0.208 3.115,1.354 3.385,1.188 true 3.76,1.344 3.51,1.177 true 2.063,1.063 2.396,0.677 true 0.833,0.854 1.344,0.656 true 0.573,0.146 0.885,0.302 0.313,0.156 10 false *a 3.823,1.052 4.281,1.25 0.458,0.198 10 false O70 2.958,1.385 3.292,1.594 0.333,0.208 10 true GND 3.667,1.385 4.115,1.563 0.448,0.177 10 true SMRP 2.281,0.156 2.552,0.313 0.271,0.156 10 true a2 1.229,0.135 1.5,0.302 0.271,0.167 10 true z9 1.813,1 2.188,1.208 0.375,0.208 10 false CEI 0.719,0.781 0.875,0.979 0.156,0.198 10 false -
*a Component without harness connected
(No. 1 Traction Battery Device Box Assembly)
- -


Standard Resistance:
Tester Connection Condition Specified Condition

Click Location & Routing(a2,z9)Location & Routing

Click Connector(a2)Body>HV Floor Under Wire>HV Battery Junction Block Assembly

Click Connector(z9)Body>other>HV Supply Battery Assembly , HV Battery Junction Block Assembly

a2-1 (CEI) - z9-1 (-) Auxiliary battery voltage not applied between terminals O70-2 (SMRP) and O70-3 (GND) 10 kΩ or higher
a2-1 (CEI) - z9-1 (-) Auxiliary battery voltage applied between terminals O70-2 (SMRP) and O70-3 (GND) 24.3 to 29.7 Ω



ii.

Measure the resistance according to the value(s) in the table below.

Standard Resistance:
Tester Connection Condition Specified Condition

Click Location & Routing(O70)Location & Routing

Click Connector(O70)Body>Floor Wire>HV Battery Junction Block Assembly

O70-2 (SMRP) - O70-3 (GND) -40 to 80°C (-40 to 176°F) 140 to 290 Ω


If the result is not as specified, replace the No. 1 traction battery device box assembly.



Hide G3850 2.INSPECT NO.1 TRACTION BATTERY DEVICE BOX ASSEMBLY (for AWD)

a.

Inspect SMRB:

i.

Measure the resistance according to the value(s) in the table below.

A413114C47
3.844,1.073 4.208,1.281 0.365,0.208 3.167,0.208 3.552,0.427 0.385,0.219 5.625,0.177 6.042,0.385 0.417,0.208 3.385,1.188 3.094,1.354 true 3.604,1.188 3.844,1.375 true 3.021,0.406 3.354,0.667 true 5.813,0.708 6.313,1.125 true 0.104,0.094 0.417,0.25 0.313,0.156 10 false *a 3.708,1.385 4.135,1.552 0.427,0.167 10 true SMRB 2.927,1.385 3.24,1.552 0.313,0.167 10 true GND 2.646,0.313 2.979,0.479 0.333,0.167 10 true CBI 3.896,1.104 4.208,1.26 0.313,0.156 10 false O70 3.292,0.24 3.542,0.406 0.25,0.167 10 true c1 6.396,1.115 6.573,1.313 0.177,0.198 10 true + 5.698,0.198 6.01,0.354 0.313,0.156 10 true z10
*a Component without harness connected
(No. 1 Traction Battery Device Box Assembly)
- -


Standard Resistance:
Tester Connection Condition Specified Condition

Click Location & Routing(c1,z10)Location & Routing

Click Connector(c1)Body>HV Battey Pack Wire>HV Battery Junction Block Assembly

Click Connector(z10)Body>other>HV Supply Battery Assembly , HV Battery Junction Block Assembly

c1-1 (CBI) - z10-1 (+) Auxiliary battery voltage not applied between terminals O70-1 (SMRB) and O70-3 (GND) 10 kΩ or higher
c1-1 (CBI) - z10-1 (+) Auxiliary battery voltage applied between terminals O70-1 (SMRB) and O70-3 (GND) Below 1 Ω



ii.

Measure the resistance according to the value(s) in the table below.

Standard Resistance:
Tester Connection Condition Specified Condition

Click Location & Routing(O70)Location & Routing

Click Connector(O70)Body>Floor Wire>HV Battery Junction Block Assembly

O70-1 (SMRB) - O70-3 (GND) -40 to 80°C (-40 to 176°F) 25.0 to 59.0 Ω


If the result is not as specified, replace the No. 1 traction battery device box assembly.



b.

Inspect SMRG:

i.

Measure the resistance according to the value(s) in the table below.

A413114C48
3.76,1.031 4.115,1.24 0.354,0.208 2.219,0.104 2.583,0.344 0.365,0.24 1.167,0.115 1.531,0.323 0.365,0.208 3.021,1.354 3.292,1.188 true 3.667,1.365 3.417,1.198 true 2.063,1.063 2.396,0.677 true 0.833,0.854 1.344,0.656 true 0.573,0.146 0.885,0.302 0.313,0.156 10 false *a 3.802,1.052 4.26,1.25 0.458,0.198 10 false O70 3.552,1.406 3.885,1.615 0.333,0.208 10 true GND 2.813,1.396 3.271,1.583 0.458,0.188 10 true SMRG 2.281,0.156 2.552,0.313 0.271,0.156 10 true c2 1.229,0.135 1.5,0.302 0.271,0.167 10 true z9 1.813,1 2.188,1.208 0.375,0.208 10 false CEI 0.719,0.781 0.875,0.979 0.156,0.198 10 false -
*a Component without harness connected
(No. 1 Traction Battery Device Box Assembly)
- -


Standard Resistance:
Tester Connection Condition Specified Condition

Click Location & Routing(c2,z9)Location & Routing

Click Connector(c2)Body>HV Battey Pack Wire>HV Battery Junction Block Assembly

Click Connector(z9)Body>other>HV Supply Battery Assembly , HV Battery Junction Block Assembly

c2-1 (CEI) - z9-1 (-) Auxiliary battery voltage not applied between terminals O70-4 (SMRG) and O70-3 (GND) 10 kΩ or higher
c2-1 (CEI) - z9-1 (-) Auxiliary battery voltage applied between terminals O70-4 (SMRG) and O70-3 (GND) Below 1 Ω



ii.

Measure the resistance according to the value(s) in the table below.

Standard Resistance:
Tester Connection Condition Specified Condition

Click Location & Routing(O70)Location & Routing

Click Connector(O70)Body>Floor Wire>HV Battery Junction Block Assembly

O70-4 (SMRG) - O70-3 (GND) -40 to 80°C (-40 to 176°F) 25.0 to 59.0 Ω


If the result is not as specified, replace the No. 1 traction battery device box assembly.



c.

Inspect SMRP:

i.

Measure the resistance according to the value(s) in the table below.

A413114C49
3.76,1.031 4.115,1.24 0.354,0.208 2.219,0.104 2.583,0.344 0.365,0.24 1.167,0.115 1.531,0.323 0.365,0.208 3.115,1.354 3.385,1.188 true 3.76,1.344 3.51,1.177 true 2.063,1.063 2.396,0.677 true 0.833,0.854 1.344,0.656 true 0.573,0.146 0.885,0.302 0.313,0.156 10 false *a 3.823,1.052 4.281,1.25 0.458,0.198 10 false O70 2.958,1.385 3.292,1.594 0.333,0.208 10 true GND 3.667,1.385 4.115,1.563 0.448,0.177 10 true SMRP 2.281,0.156 2.552,0.313 0.271,0.156 10 true c2 1.229,0.135 1.5,0.302 0.271,0.167 10 true z9 1.813,1 2.188,1.208 0.375,0.208 10 false CEI 0.719,0.781 0.875,0.979 0.156,0.198 10 false -
*a Component without harness connected
(No. 1 Traction Battery Device Box Assembly)
- -


Standard Resistance:
Tester Connection Condition Specified Condition

Click Location & Routing(c2,z9)Location & Routing

Click Connector(c2)Body>HV Battey Pack Wire>HV Battery Junction Block Assembly

Click Connector(z9)Body>other>HV Supply Battery Assembly , HV Battery Junction Block Assembly

c2-1 (CEI) - z9-1 (-) Auxiliary battery voltage not applied between terminals O70-2 (SMRP) and O70-3 (GND) 10 kΩ or higher
c2-1 (CEI) - z9-1 (-) Auxiliary battery voltage applied between terminals O70-2 (SMRP) and O70-3 (GND) 24.3 to 29.7 Ω



ii.

Measure the resistance according to the value(s) in the table below.

Standard Resistance:
Tester Connection Condition Specified Condition

Click Location & Routing(O70)Location & Routing

Click Connector(O70)Body>Floor Wire>HV Battery Junction Block Assembly

O70-2 (SMRP) - O70-3 (GND) -40 to 80°C (-40 to 176°F) 140 to 290 Ω