1.INSPECT TIE ROD END SUB-ASSEMBLY LH
Inspect the turning torque of the ball joint.
Secure the tie rod end sub-assembly LH in a vise between aluminum plates.
Do not overtighten the vise.
Install the nut to the stud bolt.
Flip the ball joint back and forth 5 times.
Set a torque wrench on the nut, turn the ball joint continuously at a rate of 2 to 4 seconds per turn, and check the turning torque on the 5th turn.
0.5 to 3.5 N*m (6 to 35 kgf*cm, 5 to 30 in.*lbf)
If the turning torque is not within the specified range, replace the tie rod end sub-assembly LH with a new one.
45046
2.INSPECT TIE ROD END SUB-ASSEMBLY RH
Use the same procedure described for the LH side.
45510
3.INSPECT STEERING GEAR ASSEMBLY TOTAL PRELOAD
Inspect the total preload.
Using SST and a torque wrench, turn the pinion shaft continuously at a rate of 4 to 6 seconds per turn to inspect the total preload of the steering gear assembly.
0.6 to 1.2 N*m (7 to 12 kgf*cm, 6 to 10 in.*lbf)
Remove the steering rack boots before measurement.
Move the steering rack through 1 or 2 full strokes to ensure that it is moving smoothly.
Inspect the total preload around the steering rack center position.
If the total preload is not within the specified range, replace the steering gear assembly with a new one.