2NR-FE EMISSION CONTROL  CANISTER  INSPECTION  


PROCEDURE

Hide 1.INSPECT CHARCOAL CANISTER

a.

Visually check the charcoal canister.

i.

Visually check the charcoal canister for cracks or damage.

If cracks or damage are found, replace the charcoal canister.



b.

Inspect the ventilation of the canister.

i.
A302971C01
0.531,0.521 1.26,0.625 false 0.917,1.656 1.844,1.198 true 0.313,0.417 0.625,0.573 0.313,0.156 10 false *a 0.719,1.583 1.031,1.74 0.313,0.156 10 false *b 2.656,1.365 2.969,1.646 0.313,0.281 10 true *c
*a Port A
*b Port B
*c Air


Apply compressed air to port B and check that the air flows out from port A.

OK:

The air flows out from the port A.




c.

Inspect the check valve.

i.
A302974C01
1.365,0.573 1.521,0.219 false 1.01,1.625 1.854,1.198 true 1.563,0.135 1.875,0.292 0.313,0.156 10 false *a 0.844,1.552 1.156,1.708 0.313,0.156 10 false *b 2.656,1.292 2.969,1.448 0.313,0.156 10 false *c
*a Port A
*b Port B
*c Air


Close the port A, and apply the compressed air from the port B.

OK:

Air does not flow at first. By gradually increasing the pressure, air flows when the pressure in the port reaches the specified level.



ii.
A302975C01
0.542,1.156 1.073,0.417 true 0.99,1.802 1.5,0.896 true 2.708,0.792 3.031,0.594 false 0.365,1.094 0.677,1.25 0.313,0.156 10 false *a 0.896,1.813 1.208,1.969 0.313,0.156 10 false *b 3.073,0.49 3.385,0.688 0.313,0.198 10 false *c
*a Port A
*b Port B
*c Vacuum Pump


Close the port A, and apply a vacuum from the port B, using a vacuum pump.

OK:

The vacuum is maintained at first. By gradually increasing the vacuum, air flows and the vacuum decreases after the vacuum reaches the specified level.