INSTALLATION
Removal / installation · Vehicles built from Nov 2005
| 1. INSTALL INTEGRATION RELAY |
Connect the 3 connectors.
Attach the integration relay to the engine room relay block.
| 2. INSTALL RELAY BLOCK COVER NO. 1 |
![]() ![]() |
Insert the stopper of the instrument panel box from the cutout of the instrument panel lower.
Engage the 2 hinges with the instrument panel open.
Close the instrument panel box.
| 3. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL |
- Torque:
- 5.4 N*m{ 55 kgf*cm , 48 in.*lbf }