Item
|
Detecting
Condition
|
Possible
cause
|
Monitoring
Strategy
|
● Rationality
check, high
|
●
Air leak in intake system ● Vacuum hose
and PCV ● Accelrator cable adjussted
improperly ● faulty ISCA ● faulty TPS ● faulty
PCSV ● Faulty PCM
|
Threshold value
|
● Eng speed -
desired eng speed : < -100 rpm
|
● Fuel cut -
off : > 2 times
|
Enable
Conditions
|
● Vehicle
speed = 0 ● Coolant temperature > 75
degC(167 °F) ● Intake air temperature
> 9.75 degC(49.55 °F) ● Altitude
(model) < 2500 m ● I-controller >
14.8 % ● Idle control
enabled
|
Diagnostic
Time
|
● 15
sec
|
Fail
Safe
|
●
None
|
| 1. |
Connect scantool to Data Link
Connector(DLC). |
| 2. |
Warm up the engine to normal operating
temperature. |
| 3. |
Monitor the "ISC actuator duty" parameter on
the scantool.

Service standard
A/CON switch OFF : 25~45%
A/CON switch ON : 35~55%
|
The data shown above is only for
reference and there may be a little difference
actually. | |
| 4. |
Is parameter displayed within
specifications?

▶ Fault is intermittent caused by poor contact
in the sensor’s and/or PCM’s connector or was repaired and PCM
memory was not cleared.Thoroughly check connectors for looseness,
poor connection, bending, corrosion,contamination,deterioration, or
damage. Repair or replace as necessary and then go to "Verification
of Vehicle Repair" proceduredure.

▶ Go to "W/Harness Inspection"
procedure. |
| TERMINAL & CONNECTOR
INSPECTION |
| 1. |
Many malfunctions in the electrical system are
caused by poor harness and terminals. Faults can also be caused by
interference from other electrical systems, and mechanical or
chemical damage. |
| 2. |
Thoroughly check connectors for looseness,
poor connection, bending, corrosion, contamination,deterioration, or
damage. |
| 3. |
Has a problem been found?

▶ Repair as necessary and go to "Verification
of vehicle Repair" procedure.

▶ Go to "Power Circuit inspection"
procedure. |
| 2. |
Disconnect ISCA
connector. |
| 3. |
.Ignition "ON" & Engine
"OFF" |
| 4. |
Measure voltage between terminal 2 of sensor
harness connector and chassis ground.

|
| 5. |
Is measure voltage within
Specification?

▶ Go to "Control circuit insepction"
procedure.

▶ Short circuit to chassis ground between ISCA
harness connector and control relay.
▶ Open circuit between ISCA harness connector
and control relay.
▶ Repair as necessary and go to "Verification
Vehicle Repair" procedure.
| 1. |
In case,when ISCA connector is
disconnected, the voltage of ISCA terminal 2 is
0V.
▶ Possible cause: Open or short
circuit in battery power line after fuse (15A
INJ). |
| 2. |
ECM also sets P1505 and P1507 if
it detects the open circuit in ISCA power
line. | | |
| CONTROL CIRCUIT
INSPECTION |
| 1. |
Check for open in harness
| (2) |
Disconnect ISCA
connector. |
| (3) |
Ignition "ON" & Engine
"OFF" |
| (4) |
Measure voltage between terminal 1 , 3
of sensor harness connector and chassis ground.

|
| (5) |
Is measure voltage within
Specification?

▶ Go to "Check for short to ground in
harness " as below.

▶ Open or Short circuit to chassis
ground between ISCA harness connector and PCM harness
connector.
▶ Repair as necessary and go to
"Verification Vehicle Repair"
procedure. | |
| 2. |
Check for short to ground in
harness
| (2) |
Disconnect ISCA connector and PCM
connector. |
| (3) |
Ignition "ON" & Engine
"OFF" |
| (4) |
Measure resistance between terminal 1 ,
3 of sensor harness connector and chassis ground.

|
| (5) |
Is measure resistance within
Specification?

▶ Go to "Check for short between open
coil and close coil harness " as below.

▶ Short circuit to chassis ground
between ISCA harness connector and PCM harness
connector.
▶ Repair as necessary and go to
"Verification Vehicle Repair"
procedure. | |
| 3. |
Check for short between open coil and close
coil harness
| (2) |
Disconnect ISCA connector and PCM
connector. |
| (3) |
Ignition "ON" & Engine
"OFF" |
| (4) |
Measure resistance between terminal 1 ,
3 of sensor harness connector.

|
| (5) |
Is measure resistance within
Specification?

▶ Go to "Component Inspection"
procedure.

▶ Shorted circuit between ISCA open
signal circuit and close signal circuit.
▶ Repair as necessary and go to
"Verification Vehicle Repair"
procedure. | |
| 1. |
Check ISCA
| (1) |
Measure resistance between terminal 2
and 3 of sensor connector(To sensor side)

|
| (2) |
Is measure resistance within
Specification?

▶ Go to "Check for ISCA sticking " as
below.

▶ Substitute with a known-good ISCA and
check for proper operation. If the problem is corrected,
replace ISCA and then go to "Verification of Vehicle Repair"
procedure. | |
| 2. |
Check for ISCA sticking.
| (2) |
Check that ISCA actuator valve is clean
and not sticking. |
| (3) |
Check that throttle lever return spring
is clean and sticking. |
| (4) |
Check intake air system and vacuum hoses
to intake air system. |
| (5) |
Are the results of these checks
OK?

▶ Substitute with a known-good PCM and
check for proper operation. If the problem is corrected,
replace PCM and then go to "Verification of Vehicle Repair"
procedure.

▶ Substitute with a known-good ISCA and
check for proper operation. If the problem is corrected,
replace ISCA and then go to "Verification of Vehicle Repair"
procedure. | |
| VERIFICATION OF VEHICLE
REPAIR |
| 1. |
Monitor and record the Freeze Frame Data for
the Diagnostic Trouble Code (DTC) which has been
diagnosed. |
| 2. |
Using a Scantool, Clear the
DTCs. |
| 3. |
Operate the vehicle within conditions noted in
the freeze frame data or enable
conditions. |
| 4. |
Monitor that all rediness test have been
verified as "Complete" |
| 5. |
Are any DTCs present ?

▶ Go to the applicable troubleshooting
procedure.

▶ System is performing to specification at