Item
|
Detecting Condition
|
Possible cause
|
Monitoring Strategy
|
● Circuit continuity check, high
|
● Short to battery in control
circuit ● Faulty PCSV ● Faulty PCM
|
Threshold value
|
● Short circuit to battery
|
Enable Conditions
|
● Short circuit
|
Diagnostic Time
|
● continous
|
Fail Safe
|
● None
|
| 1. |
Connect scantool to Data Link
Connector(DLC). |
| 2. |
Warm up the engine to normal operating
temperature. |
| 3. |
Monitor the "EVAP.PURGE VALVE" parameter on
the scantool.

|
The data shown above is only for
reference and there may be a little difference
actually. |
Service standard
Idle : 0 %
1000~3000 rpm : 1.5 ~ 35
% |
| 4. |
Is parameter displayed within
specifications?

▶ Fault is intermittent caused by poor
contact in the sensor’s and/or PCM’s connector or was repaired and
PCM memory was not cleared.Thoroughly check connectors for
looseness, poor connection, bending,
corrosion,contamination,deterioration, or damage. Repair or replace
as necessary and then go to "Verification of Vehicle Repair"
procedure.

▶ Go to "W/Harness Inspection"
procedure. |
| TERMINAL & CONNECTOR
INSPECTION |
| 1. |
Many malfunctions in the electrical system
are caused by poor harness and terminals. Faults can also be caused
by interference from other electrical systems, and mechanical or
chemical damage. |
| 2. |
Thoroughly check connectors for looseness,
poor connection, bending, corrosion, contamination,deterioration, or
damage. |
| 3. |
Has a problem been found?

▶ Repair as necessary and go to
"Verification of vehicle Repair" procedure.

▶ Go to "Control circuit insepction"
procedure. |
| CONTROL CIRCUIT
INSPECTION |
| 1. |
Check for short to power in
harness
| (2) |
Disconnect PCSV sensor
connector. |
| (3) |
Ignition "ON" & Engine
"OFF" |
| (4) |
Measure voltage between terminal 2 of
PCSV harness connector and chassis ground.

|
| (5) |
Is measure voltage within
Specification?

▶ Go to "Component Inspection"
procedure.

▶ Short circuit to chassis ground
between PCSV harness connector and PCM harness
connector.
▶ Repair as necessary and then go to
"Verification of Vehicle Repair" procedure.
|
In case the voltage at terminal
1 of PCSV is 12 V when PCSV is
disconnected.
▶ Possible cause : Short circuit
in battery power line after fuse(15A
INJ) | | |
| 1. |
Check PCSV
| (1) |
Measure resistance between terminal 1
and 2 of sensor connector(To sensor side)

|
| (2) |
Is measure resistance within
Specification?

▶ Substitute with a known-good PCM and
check for proper operation. If the problem is corrected,
replace PCM and then go to "Verification of Vehicle Repair"
procedure.

▶ Substitute with a known-good PCSV
and check for proper operation. If the problem is corrected,
replace PCSV and then go to "Verification of Vehicle Repair"
procedure.
|
The purpose of measuring
injector resistance is to find if the open circuit is in
the component.So,check the continuity between signal
line and ground
line. | | |
| VERIFICATION OF VEHICLE
REPAIR |
| 1. |
Monitor and record the Freeze Frame Data for
the Diagnostic Trouble Code (DTC) which has been
diagnosed. |
| 2. |
Using a Scantool, Clear the
DTCs. |
| 3. |
Operate the vehicle within conditions noted
in the freeze frame data or enable
conditions. |
| 4. |
Monitor that all rediness test have been
verified as "Complete" |
| 5. |
Are any DTCs present ?

▶ Go to the applicable troubleshooting
procedure.

▶ System is performing to specification at
this time. |

|