The HECU supplies
battery power to all solonid valves with a valve relay which is controlled
by the Electronic Control UNIT(ECU). The valve relay and all solenoid
valves are installed inside the HECU ( Hydraulic and Electronic Control
Unit ).
The HECU monitors
voltage of the valve relay to check if the HECU can perform ABS control
normally. When the valve relay is switched to ON, the HECU will set this
code if the solenoid drive voltage is below permissible voltage ranges for
a period of time. When the valve relay is switched to OFF, the HECU sets
this code if the solenoid drive voltage is over the permissible voltage
range for a period of time.
Item
|
Detecting
Condition
|
Possible cause
|
DTC Strategy
|
|
| •
|
Open or short in power supply circuit
(IGN+) | |
Case1
|
Monitoring Period
|
|
Enable Conditions
|
| •
|
Watchdog and valve relay function is
tested during startup.
A failure is detected if the valve
relay/Enable remains in off position when it is turned on and
vice versa. Reason could be short to GND or UZ, interrupted
lines or a defective output stage
etc. | |
Case2
|
Monitoring Period
|
|
Enable Conditions
|
| •
|
A Fault is detected if valve relay
voltage < 0.8 * battery voltage for a time
500ms. | |
Case3
|
Monitoring Period
|
|
Enable Conditions
|
| •
|
If valve relay malfunction and supply
solenoid valve short to battery or supply solenoid valve and
medium or high ohmic short of valve relay (or a valve) to
valve relay voltage, solenoid valve voltage or GND are
detected. | |
Fail Safe
|
| •
|
No valve actuation
possible. |
| •
|
The ABS/EBD/ESC functions are
inhibited. |
| •
|
The ABS/EBD/ESC warning lamps are
activated.
| |
| Terminal and Connector
Inspection |
| 1. |
Many malfunctions in the electrical system are
caused by poor harness(es) and terminals. Faults can also be caused
by interference from other electrical systems, and mechanical or
chemical damage. |
| 2. |
Thoroughly check connectors for looseness,
poor connection, bending, corrosion, contamination, deterioration,
or damage. |
| 3. |
Has a problem been found?
|

|
▶ Repair as
necessary and then go to "Verification of Vehicle Repair"
procedure.
|
|

|
▶ Go to
"Power Circuit Inspection"
procedure.
|
|
| Power Supply Circuit
Inspection |
| 2. |
Disconnect HECU
connector. |
| 4. |
Measure voltage between terminal "3" of the
HECU harness connector and chassis ground.
Specification
: Approx. B+
|

|
| 5. |
Is the measured voltage within
specifications?
|

|
▶ Go to
"Ground Circuit Inspection" procedure.
|
|

|
▶ Check for
damaged harness and open or short to GND between the battery
terminal(+) and terminal "3" of the HECU harness connector.
Check for open or blown 20A ABS fuse referring to "Circuit
Diagram". Repair as necessary and then go to "Verification of
vehicle Repair"
procedure.
|
|
| Ground Circuit
inspection |
| 2. |
Disconnect HECU
connector. |
| 3. |
Measure resistance between terminal "4" of the
HECU harness connector and chassis ground.
Specification
: Approx. below 1Ω
|

|
| 4. |
Is the measured resistance within
specifications?
|

|
▶ Go to
"Component Inspection" procedure.
|
|

|
▶ Check for
damaged harness and poor connection between terminal "4" of
the HECU harness connector and chassis ground. Repair as
necessary and then go to "Verification of vehicle Repair"
procedure.
|
|
| 3. |
Does warning lamp remain On?
|

|
▶
Substitute with a known-good HECU and check for proper
operation. If problem is corrected, replace HECU and then go
to "Verification of Vehicle Repair"
procedure.
|
|

|
▶ Fault is
intermittent caused by faulty HECU or was repaired and HECU
memory was not cleared. Go to the applicable troubleshooting
procedure.
|
|
| Verification of Vehicle
Repair |
After a repair, it is
essential to verify that the fault has been corrected.
| 1. |
Connect scantool and select "Diagnostic
Trouble Codes(DTCs)" mode |
| 2. |
Using a scantool, Clear
DTC. |
| 3. |
Operate the vehicle within DTC Detecting
Condition in General Information. |
| 4. |
Are any DTCs present ?
|

|
▶ Go to the
applicable troubleshooting procedure.
|
|

|
▶ System
performing to specification at this
time.
|
|