| 1. |
Remove the LH/RH cylinder head cover.
(Refer to Cylinder Head Assembly - "Cylinder
Head Cover") |
| 2. |
Remove the lower oil pan.
(Refer to Lubrication System - "Oil
Pan") |
| 3. |
Remove the drive belt auto tensioner.
(Refer to Timing System - "Drive Belt
Tensioner") |
| 4. |
Remove the crankshaft damper pulley.
(Refer to Timing System - "Crankshaft Damper
Pulley") |
| 5. |
Remove the engine mounting bracket.
(Refer to Engine And Transmission Assembly -
"Engine Mounting") |
| 6. |
Lift up the engine assembly slightly by
using a jack to get access to the side of
engine. |
| 7. |
Remove the water pump and gasket.
(Refer to Cooling System - "Water
Pump") |
| 8. |
Remove the timing chain cover
(A).

|
Be careful not to damage the contact
surfaces of cylinder block, cylinder head and timing chain
cover. | |
| 1. |
Install the timing chain cover.
| (1) |
The sealant locations on chain cover
and on counter parts (cylinder head, cylinder block, and lower
oil pan) must be free of engine oil and
etc. |
| (2) |
Before assembling the timing chain
cover, the liquid sealant TB 1217H (Hyundai Gray RTV) should
be applied on the gap between cylinder head and cylinder
block. The part must be assembled within 5 minutes after
sealant was applied.
Bead
width :
2.5mm(0.1in.)
|

|
| (3) |
After applying liquid sealant TB 1217H
(Hyundai Gray RTV) on timing chain cover. The part must be
assembled within 5 minutes after sealant was
applied.
Sealant should be applied without
discontinuity.

| • |
Fill the T-joint area (6EA
*) with sealant. |
| • |
Apply sealant all around
the dowel pin hole
(2EA). | | |
| (4) |
Install the new gasket (A) to the
timing chain cover.

|
During timing cover
installation, care not to take off applied sealant on
the timing cover by contact with other
parts. | |
| (5) |
The dowel pins on the cylinder block
and holes on the timing chain cover should be used as a
reference in order to assemble the timing chain cover to be in
exact position.
Tightening
torque
A (17EA) :
18.6 ~ 21.6N.m (1.9 ~ 2.2kgf.m,
13.7 ~ 15.9lb-ft)
B (2EA) :
24.5 ~ 26.5N.m (2.5 ~ 2.7kgf.m,
18.1 ~ 19.5lb-ft)
C (1EA) :
58.8 ~ 68.8N.m (6.0 ~ 7.0kgf.m,
43.4 ~ 50.6lb-ft)
D (1EA) :
58.8 ~ 68.8N.m (6.0 ~ 7.0kgf.m,
43.4 ~ 50.6lb-ft)
E (3EA) :
9.8 ~ 11.8N.m (1.0 ~ 1.2kgf.m,
7.2 ~ 8.7lb-ft)
|

|
| (6) |
Running the engine or performing a
pressure test should not be performed within 30 minutes of
assembly. | |
| 2. |
Install the front oil seal.
(Refer to Timing System - "Front Oil
Seal") |
| 3. |
Install the other parts reverse order of
removal.
| • |
Clean the battery posts and
cable terminals with sandpaper. Assemble and then apply
grease to prevent corrosion.
|
| • |
Inspect for fuel leakage.
|
| - |
After assembling the fuel line,
turn on the ignition switch (do not operate the starter)
so that the fuel pump runs for approximately two seconds
and fuel line pressurizes.
|
| - |
Repeat this operation two or
three times, then check for fuel leakage at any point in
the fuel lines. |
| • |
Refill radiator and reservoir
tank with engine coolant.
|
| • |
Bleed air from the cooling
system. |
| - |
Start engine and let it run
until it warms up. (Until the radiator fan operates 3 or
4 times.) |
| - |
Turn Off the engine and let it
cool down. Check the level in the radiator, add coolant
if needed. This will allow trapped air to be removed
from the cooling system.
|
| - |
Put radiator cap on tightly,
then run the engine again and check for
leaks. | | | |