| 1. |
Measure the pressure of high pressure line by
measuring voltage output between terminal "1" and "2".

|
| 2. |
Inspect the voltage value whether it is
sufficient to be regular value or not.
Vout = 0.00878835 * P +
0.37081095
| |
| 3. |
If the measured voltage value is not within
the specification, replace the A/C pressure
transducer. |
| 1. |
Disconnect the negative (-) battery
terminal. |
| 2. |
Recover the refrigerant with a
recovery/charging station. |
| 3. |
Disconnect the A/C pressure transducer
connector (A).

|
| 4. |
Remove the A/C pressure transducer
(A).
Tightening
torque:
10.0 ~ 12.0 N.m (1.02~ 1.22 kgf.m,
7.4~8.8 lb-ft)
|

| •
|
Be careful not to bend the liquid
& suction
pipe. | | |
| 5. |
Install in the reverse order of
removal.

| •
|
When installing, replace it with a
new O-ring
(A). | | | |