| 1. |
Remove the timing chain.
(Refer to Timing system in this
group)
|
Before removing the balance shaft chain,
set the crankshaft key right direction to TDC position as
following
picture. | |
| 2. |
Install a set pin after compressing the
balance shaft chain tensioner and then remove the hydraulic
tensioner (A). |
| 3. |
Remove the balance shaft chain tensioner arm
(B). |
| 4. |
Remove the balance shaft chain guide
(C).

|
| 5. |
Remove the oil pump & balance shaft module
(A) and balance shaft chain (B).

|
Do not disassemble the oil pump &
balance shaft
module. | |
| 1. |
The key of crankshaft should be aligned with
the mating face of main bearing cap. As a result of this, the piston
of No.1 cylinder is placed at the top dead center on compression
stroke. |
| 2. |
Install the balance shaft chain that the
timing mark of crankshaft should be matched with timing mark (color
link) of balance shaft chain.

|
| 3. |
Install the balance shaft module that the
timing mark of balance shaft module sprocket should be matched with
timing mark (color link) of balance shaft chain.

|
The balance shaft sprocket mark (A)
should be matched with balance shaft housing timing mark (B)
during installation. |

|
| 4. |
Install the balance shaft bolt &
washer.
Bolting order
| A. |
Assemble the bolts in order number as
shown with seating torque 26.5 N.m (2.7kgf.m, 19.5 lb-ft)
|
| B. |
Unfasten the bolts as reverse bolting
order. (4-3-2-1) to minimize tighten torque err from bushing
and sealant. |
| C. |
Assemble the bolts as specified bolting
order in same increments as
follows. |
Tightening
torque :
22.6~26.5N.m (2.3~2.7kgf.m,
16.6~19.5lb-ft) + (103~107°)
|

|
| 5. |
Install the balance shaft chain guide
(C).
Tightening
torque :
9.8 ~ 11.8N.m (1.0 ~ 1.2kgf.m, 7.2 ~
8.7lb-ft)
| |
| 6. |
Install the balance shaft chain tensioner arm
(B).
Tightening
torque :
9.8 ~ 11.8N.m (1.0 ~ 1.2kgf.m, 7.2 ~
8.7lb-ft)
| |
| 7. |
Install the balance shaft chain hydraulic
tensioner (A) then remove the stopper pin.
Tightening
torque :
9.8 ~ 11.8N.m (1.0 ~ 1.2kgf.m, 7.2 ~
8.7lb-ft)
|

|
If replaced new balance shaft module,the
pin (D) is to be
removed. | |
| 8. |
Confirm the timing marks.
|
| 9. |
Install the timing chain.
(Refer to Timing system in this
group) | |