Home › Automatic Transaxle System › Troubleshooting

P0890 AT Relay - Low Circuit

COMPONENT LOCATION

GENERAL DESCRIPTION
The automatic transmission supplies power to the solenoid valves by way of a control relay. When the PCM sets the relay to ON, the relay operates and the battery power is supplied to all the sonenoid valves. When the PCM sets the relay to OFF, all solenoid valve power is shut off and the transmission is held in the 3rd gear position. (Fail Safe Mode)
DTC DESCRIPTION
The PCM checks the A/T control relay signal by monitoring the control signal. If, the voltage applied to A/T solenoids is lower than 0.5V, the PCM sets this code.
DTC DETECTING CONDITION
Item
Detecting Condition & Fail Safe
Possible cause
DTC Strategy
•
Check voltage range
•
Open or short in circuit
•
Faulty A/T control relay
•
Faulty PCM
Enable Conditions
•
Engine state≠Power off relay or engine shutdown process
•
Battery voltage>11V and<16V
•
A/T power relay is enabled
•
No TCM power relay diag fail
Threshold value
•
Voltage applied to A/T solenoids<= 0.5 V
Diagnostic Time
•
2 seconds
Fail Safe
•
Locked in 3rd gear.(Control relay off)

MONITOR SCANTOOL DATA
1.
Connect scantool to data link connector(DLC).
2.
Ignition "ON" & Engine "OFF".
3.
Monitor the "A/T CON. RELAY VOLT" parameter on the scantool.

Specification : Approx. B+

4.
Is A/T RELAY VOLT within specifications?

▶ Fault is intermittent caused by poor contact in the sensor's and/or PCM's connector or was repaired and PCM memory was not cleared. Thoroughly check connectors for looseness, poor connection, bending, corrosion, contamination, deterioration or damage. Repair or replace as necessary and go to "Verification vehicle repair" procedure.

▶ Go to "Terminal&connector inspection" procedure.
TERMINAL & CONNECTOR INSPECTION
1.
Many malfunctions in the electrical system are caused by poor harness and terminals. Faults can also be caused by interference from other electrical systems, and mechanical or chemical damage.
2.
Thoroughly check connectors for looseness, poor connection, bending, corrosion, contamination, deterioration, or damage.
3.
Has a problem been found?

▶ Repair as necessary and then go to "Verification of vehicle repair" procedure.

▶ Go to "Power supply circuit inspection" procedure.
POWER SUPPLY CIRCUIT INSPECTION
1.
Ignition "ON" & Engine "OFF".
2.
Disconnect the "A/T CONTROL RELAY" connector.
3.
Measure the voltage between the power terminal of the "A/T CONTROL RELAY" in the engine room relay box and chassis ground.

Specification : Approx. B+

4.
Is voltage within specifications?

▶ Go to "Signal circuit inspection" procedure.

▶ Check that A/T-20A fuse in engine room junction is installed or not blown.
▶ Check for Open in harness. Repair as necessary and go to "Verification vehicle repair" procedure.
SIGNAL CIRCUIT INSPECTION
1.
CHECK A/T control relay harness
(1)
Ignition "OFF".
(2)
Disconnect the "ATM CONTROL RELAY" connector.
(3)
Measure the voltage between terminal "60" of the "PCM" harness connector A and chassis ground.
(4)
Turn ignition switch OFF → ON.

Specification: 12V is measured only for approx. 0.5sec

(5)
Is voltage within specifications?

▶ Go to "Check supplying power to solenoid valve" procedure.

▶ Check for open in harness. Repair as necessary and go to "Verification vehicle repair" procedure
▶ If signal circuit is OK, Substitute with a known-good PCM and check for proper operation. If the problem is corrected, replace PCM and then go to "Verification of vehicle repair" procedure.
2.
CHECK supplying power to solenoid valve harness
(1)
Ignition "OFF".
(2)
Disonnect the "ATM CONTROL RELAY" and PCM connector.
(3)
Measure the resistance between the terminal shown below of the "A/T CONTROL RELAY" in the engine room relay box and terminal "20" of the PCM harness connector A.

Specification : Approx. 0 Ω

(4)
Is resistance within specifications?

▶ Go to "Ground circuit inspection" procedure.

▶ Check for open in harness. Repair as necessary and go to "Verification vehicle repair" procedure.
GROUND CIRCUIT INSPECTION
1.
Ignition "OFF".
2.
Disconnect the "A/T CONTROL RELAY" connector.
3.
Measure the resistance between the terminal shown below of the "A/T CONTROL RELAY" in the engine room relay box and chassis ground.

Specification : Approx. 0 Ω

4.
Is resistance within specifications?

▶ Go to "Component inspection" procedure.

▶ Check for open in harness. Repair as necessary and go to "Verification vehicle repair" procedure.
COMPONENT INSPECTION
1.
Ignition "OFF".
2.
Remove "A/T CONTROL RELAY"
3.
Measure the resistance between each terminal of the sensor.

Specification: ∞ except between those two terminals below

4.
Is resistance with in specification?

▶ Thoroughly check connectors for looseness, poor connection, bending, corrosion, contamination, deterioration, or damage. Repair or replace as necessary and then go to "Verification of vehicle repair" procedure.

▶ Replace ATM CONTROL RELAY and then go to "Verification of vehicle repair" procedure.
VERIFICATION OF VEHICLE REPAIR
After a repair, it is essential to verify that the fault has been corrected.
1.
Connect scan tool and select "Diagnostic Trouble Codes(DTCs)" mode.
2.
Using a scantool, Clear DTC.
3.
Operate the vehicle within DTC Enable conditions in General information.
4.
Are any DTCs present ?

▶ Go to the applicable troubleshooting procedure.

▶ System performing to specification at this time.