Home › Fuel System › Engine Control System › Engine Control Module (ECM)

Engine Control System › Engine Control Module (ECM): Repair procedures

REPLACEMENT
1.
Disconnect the ECM wiring connector.
2.
Unscrew four bolts mounting on back of air cleaner assembly.

3.
Remove the ECM.
4.
Install a new ECM.

Tightening torque: 1.0 ~ 1.2kgf·m

5.
Write the VIN (Vehicle Identification Number) in a new ECM according to "VIN PROGRAMMING PROCEDURE" (Refer to FL-43).
6.
Perform the below procedeures to program an new TPS adaptation into a new ECM.
When replacing ECM or ETC throttle body, be sure to perform a new TPS adaptation using Hi-Scan(Pro).
1.
Clear the previous TPS adaptation value using Hi-Scan(Pro).

2.
Turn the iginition switch off, and then turn it on without cranking.
3.
Wait for 10sec. until TPS adaptation finishes.
The above procedures have to be performed under below conditions.
•
Battery voltage >10V
•
Intake air temperature >5.3°C
•
5.3°C< Coolant temperature< 99.8°C
7.
Check a fault code(DTC) on Hi-Scan(Pro) if the TPS adaptation was successful.
ECM PROBLEM INSPECTION PROCEDURE
1.
TEST ECM GROUND CIRCUIT: Measure resistance between ECM(pin NO. 1, 2, 3) and chassis ground using the backside of ECM harness connector as ECM side check point. If the problem is found, repair it.

Specification (Resistance)
Between terminal 1 of C230-1 connector and chassis ground : 1Ω or less
Between terminal 2 of C230-1 connector and chassis ground : 1Ω or less

2.
TEST ECM CONNECTOR: Disconnect the ECM connector and visually check the ground terminals on ECM side and harness side for bent pins or poor contact pressure. If the problem is found, repair it.
3.
If problem is not found in Step 1 and 2, the ECM could be faulty. If so, replace the ECM with a new one, and then check the vehicle again. If the vehicle operates normally then the problem was likely with the ECM.
4.
RE-TEST THE ORIGINAL ECM : Install the original ECM (may be broken) into a known-good vehicle and check the vehicle. If the problem occurs again, replace the original ECM with a new one. If problem does not occur, this is intermittent problem (Refer to INTERMITTENT PROBLEM PROCEDURE in BASIC INSPECTION PROCEDURE)
ECM PROBLEM INSPECTION PROCEDURE
1.
TEST ECM GROUND CIRCUIT: Measure resistance between ECM(pin NO. 1, 2, 3) and chassis ground using the backside of ECM harness connector as ECM side check point. If the problem is found, repair it.

Specification (Resistance)
Between terminal 1 of C230-1 connector and chassis ground : 1Ω or less
Between terminal 2 of C230-1 connector and chassis ground : 1Ω or less

2.
TEST ECM CONNECTOR: Disconnect the ECM connector and visually check the ground terminals on ECM side and harness side for bent pins or poor contact pressure. If the problem is found, repair it.
3.
If problem is not found in Step 1 and 2, the ECM could be faulty. If so, replace the ECM with a new one, and then check the vehicle again. If the vehicle operates normally then the problem was likely with the ECM.
4.
RE-TEST THE ORIGINAL ECM : Install the original ECM (may be broken) into a known-good vehicle and check the vehicle. If the problem occurs again, replace the original ECM with a new one. If problem does not occur, this is intermittent problem (Refer to INTERMITTENT PROBLEM PROCEDURE in BASIC INSPECTION PROCEDURE)