To reduce the required
power to manipulate steering wheel, hydraulic pressure is used in power
steering system. A load is sensed at steering oil pressure sensor then
inputted to PCM as a wheel position signal. Controlling idle speed valve,
PCM performs appropriate electric load correction With this
signal.
Checking output signals
from P/S PS(power steering pressure sensor) every 2.5 sec. under detecting
condition, if an signal below 0.05V lasts for more than 1.25 sec., PCM
sets P0552. MIL(Malfunction Indicatin Lamp) turns on when the malfunction
lasts till cosecutive 2 driving cycle.
Item
|
Detecting
Condition
|
Possible cause
|
DTC Strategy
|
| •
|
Detects sensor signal short to low
voltage | |
| •
|
Short in signal
circuit |
| •
|
Faulty P/S pressure
sensor |
|
Enable Conditions
|
| •
|
11V ≤ Battery voltage ≤
16V | |
Thresh old value
|
| •
|
Sensor output voltage
>4.65V | |
Diagnosis Time
|
| •
|
Continuous
(More than 1.25 seconds failure for
every 2.5 seconds test
) | |
MIL On Condition
|
|
Pressure(Kgf/cm²)
|
37.9
|
41.3
|
68.8
|
96.4
|
Voltage(V)
|
1
|
2
|
3
|
4
|

| 2. |
Connect Scantool and Engine
"ON" |
| 3. |
Check whether steering pressure is rising
during operating. (Keep the idling status)

|
| 4. |
Are those items on scantool displayed
correctly ?

▶ Fault is intermittent caused by poor contact
in Sensor’s and/or PCM’s connector or was repaired and PCM memory
was not cleared. Thoroughly check connectors for looseness, poor
connection, bending, corrosion, contamination, deterioration, or
damage. Repair or replace as necessary and go to "Verification of
Vehicle Repair" procedure

▶ Go to "Terminal and Connector Inspection"
procedure. |
| TERMINAL AND CONNECTOR
INSPECTION |
| 1. |
Many malfunctions in the electrical system are
caused by poor harness and terminals. Faults can also be caused by
interference from other electrical systems, and mechanical or
chemical damage. |
| 2. |
Thoroughly check connectors for looseness,
poor connection, bending, corrosion, contamination, deterioration,
or damage. |
| 3. |
Has a problem been found?

▶ Repair as necessary and go to "Verification
of Vehicle Repair" procedure

▶ Go to " Power Circuit Inspection "
procedure. |
| 2. |
Disconnect the P/S pressure sensor
connector. |
| 4. |
Measure the voltage between terminal 3 of P/S
pressure sensor harness connector and chassis ground.
Specification : approx.
5V
|

|
| 5. |
Is the measured voltage within specification
?

▶ Go to "Ground circuit inspection"
procedure.

▶ Repair Short in power circuit and go to
"Verification of Vehicle Repair"
procedure. |
| GROUND CIRCUIT
INSPECTION |
| 2. |
Disconnect the P/S pressure sensor
connector. |
| 4. |
Measure the voltage between terminal 3 of P/S
pressure sensor harness connector and chassis ground. (Fig
A) |
| 5. |
Measure the voltage between terminal 3 and
terminal 1 of P/S pressure sensor harness connector. (Fig
B)
Specification : The Difference between
"A" and "B" is below 200mV.
|

|
| 6. |
Is the measured voltage within specification
?

▶ Go to "Signal circuit inspection"
procedure.

▶ Repair as necessary and go to "Verification
of Vehicle Repair" procedure. |
| SIGNAL CIRCUIT
INSPECTION |
| 1. |
Check short in harness
| (2) |
Disconnect P/S pressure sensor connector
and PCM connector. |
| (3) |
Measure the resistance between terminal
2 and terminal 3 of P/S pressure sensor harness
connector.

|
| (4) |
Is the measured resistance within
specification ?

▶ Go to "Component inspection"
procedure.

▶ Repair Short in signal circuit and go
to "Verification of Vehicle Repair"
procedure. | |
| 1. |
P/S pressure sensor inspection
| (1) |
Key "OFF" and connect the
scantool. |
| (2) |
Connect the probe to signal line of P/S
pressure sensor and select the oscilloscope in
menu. |
| (3) |
Check the waveform with steering handle
movement after engine start.
Specification :
Pressure(Kgf/cm²)
|
37.9
|
41.3
|
68.8
|
96.4
|
Voltage(V)
|
1
|
2
|
3
|
4
|

|
| (4) |
Is the measured waveform of P/S pressure
sensor normal?

▶ Substitute with a known - good PCM and
check for proper operation. If the problem is corrected,
replace PCM and go to "Verification of Vehicle Repair"
procedure.

▶ Substitute with a known - good P/S
pressure sensor and check for proper operation. If the problem
is corrected, replace P/S pressure sensor and go to
"Verification of Vehicle Repair" procedure.
|
There is a memory reset function
on scantool that can erase optional parts automatically
detected and memorized by PCM. After testing PCM on the
vehicle, use this function to reuse the PCM on the
others | | |
| VERIFICATION OF VEHICLE
REPAIR |
After a repair, it is
essential to verify that the fault has been corrected.
| 1. |
Monitor and record the Freeze Frame Data for
the Diagnostic Trouble Code(DTC) which has been
diagnosed. |
| 2. |
Using a Scantool, Clear the
DTCs |
| 3. |
Operate the vehicle within conditions noted in
the freeze frame data or enable
conditions |
| 4. |
Monitor that all rediness test have been
verified as " Complete " |
| 5. |
Are any DTCs present ?

▶ Go to the applicable troubleshoooting
procedure.

▶ System is performing to specification at
this
time. |