INSTALLATION
Removal / installation
| 1. INSTALL ROOF DRIP SIDE FINISH MOULDING CLIP NO.1 |
- HINT:
- Only when replacing the clips.
Remove the tape that remains on the mounting surface of the body and then clean the surface with white gasoline.

Using a heat light, heat up the clip installation surfaces of the body and moulding.
- Heating temperature:
Body
40 to 60°C (104 to 140°F)
Moulding
20 to 30°C (68 to 86°F)
- NOTICE:
- Do not heat them excessively.
Set the new clips into the positions as shown in the illustration, and press-fit those clips by hands to install them.
The installation of the moulding should be carried out when 30 minutes or more have passed after press-fitting the clips.
- HINT:
- Initial hardening time is 30 minutes
- Hardening completes after 24 hours
- Initial hardening time is 30 minutes
| 2. INSTALL ROOF DRIP SIDE FINISH MOULDING REAR |
| 3. INSTALL ROOF DRIP SIDE FINISH MOULDING CENTER |
| 4. INSTALL ROOF DRIP SIDE FINISH MOULDING CENTER |
| 5. INSTALL ROOF DRIP SIDE FINISH MOULDING |
| 6. INSTALL ROOF DRIP SIDE MOULDING COVER FRONT |