INSTALLATION
Removal / installation · Vehicles built from Jun 2009
Versions by build date: Jun 2006 – Sep 2006 Oct 2006 – May 2009 from Jun 2009
| 1.
INSTALL FLOOR SHIFT LEVER ASSEMBLY |
 |
- Install the shift lever assembly with the 4 bolts.
-
Torque:
- 12 N*m{
122 kgf*cm
, 9 ft.*lbf
}
| 2.
INSTALL TRANSMISSION CONTROL CABLE ASSEMBLY |
 |
- Connect the control cable to the shift lever retainer.
- NOTICE:
- The projecting part of the cable outer should face upward when the shift cable is connected.
- After installation, make sure that the cable outer lock is projecting from A as shown in the illustration.
- Connect the end of the shift cable to the shift lever assembly with the clip.
Connect the end of the select cable to the shift lever assembly with a new clip.
- NOTICE:
- The serrated part of the select cable point should face upward when the select cable point is connected.
- The clip should be installed in the direction as shown in the illustration.
| 3.
INSTALL UPPER CONSOLE REAR PANEL SUB-ASSEMBLY
|
 |
- Engage the 3 claws and 5 clips to install the upper console rear panel sub-assembly.
| 4.
INSTALL UPPER CONSOLE PANEL
|
 |
- Engage the 2 claws and the 5 clips to install the upper console panel as shown in the illustration.
| 5.
INSTALL NO. 2 INSTRUMENT CLUSTER FINISH PANEL GARNISH
|
 |
- Engage the 2 clips and install the No. 2 instrument cluster finish panel garnish.
| 6.
INSTALL NO. 1 INSTRUMENT CLUSTER FINISH PANEL GARNISH
|
 |
- Engage the 2 clips and install the No. 1 instrument cluster finish panel garnish.
| 7.
INSTALL SHIFT LEVER KNOB SUB-ASSEMBLY
|
 |
- Install the shift lever knob sub-assembly.