1.INSTALL INJECTION NOZZLES
Place new gaskets and the nozzle seats into the injection nozzle holes of the cylinder head.
Using SST, install the injection nozzles.
650 kg*cm (47 ft*lb, 64 N*m)
Over torquing could cause nozzle deformation and needle adhesion or other defects.
When installing the injection nozzle, never torque the nozzle holder body. Torque the retaining nut section.
23760
2.INSTALL NOZZLE LEAKAGE PIPE
Install new gaskets and the leakage pipe with the nuts.
300 kg*cm (22 ft*lb, 29 N*m)
Connect the fuel hose to the return pipe.
3.INSTALL INJECTION PIPES
Place the two clamps on the intake manifold.
Connect the injection pipes to injection nozzle.
150 kg*cm (11 ft*lb, 15 N*m)
Connect the injection pipes to injection pump.
150 kg*cm (11 ft*lb, 15 N*m)
Secure the injection pipes with clamps and bolts.
4.INSTALL INTAKE PIPE
5. START ENGINE AND CHECK FOR FUEL LEAKS