2011-2016 FJ Cruiser · Service Manual ENGINE

REASSEMBLY

Removal / installation · Vehicles built Jul 2007 – Jul 2009

Versions by build date: Jul 2007 – Jul 2009 from Aug 2009


1. INSTALL STARTER ARMATURE ASSEMBLY
  1. Apply grease to the bearings, and install them onto the stater yoke.


2. INSTALL STARTER BRUSH HOLDER ASSEMBLY
  1. Install the a new O-ring onto the groove of the starter yoke assembly.

  1. Place the brush holder on the armature.

  1. A062429
    Using a screwdriver, install 4 brushes.

  1. A062428
    Install the commutator end frame with the 2 screws.

    Torque:
    3.8 N*m{ 39 kgf*cm , 34 in.*lbf }


3. INSTALL MAGNET STARTER SWITCH ASSEMBLY
  1. Apply grease to the steel ball, and install it onto the clutch shaft hole.

  1. A062427E01
    Apply grease to parts (2) to (5), and install all the parts below onto the starter drive housing.
    (1)
    Starter magnet switch return spring
    (2)
    Starter idle gear pinion
    (3)
    Starter idle gear clutch roller
    (4)
    Starter idle gear retainer
    (5)
    Starter clutch

  1. A074097
    Install the magnet starter switch with the 2 screws.

    Torque:
    9.3 N*m{ 95 kgf*cm , 82 in.*lbf }


4. INSTALL STARTER YOKE ASSEMBLY
  1. Install a new O-ring onto the groove of the starter yoke.

  1. A076121
    Align the key of the starter yoke with the groove of the magnet starter switch.

  1. A074096
    Install the starter yoke and armature with the 2 through bolts.

    Torque:
    9.3 N*m{ 95 kgf*cm , 82 in.*lbf }

  1. Connect the lead wire to terminal C with the nut.

    Torque:
    5.9 N*m{ 60 kgf*cm , 52 in.*lbf }