2011-2016 FJ Cruiser · Service Manual ENGINE

INSTALLATION

Removal / installation · Vehicles built from Aug 2014

Versions by build date: Jul 2007 – Jul 2009 Aug 2009 – Jul 2014 from Aug 2014


1. INSTALL PURGE VSV
  1. Install the purge VSV with the bolt.

    Torque:
    9.0 N*m{ 92 kgf*cm , 80 in.*lbf }

  1. Connect the No. 1 fuel vapor feed hose and fuel vapor feed hose.

  1. Connect the purge VSV connector.


2. INSTALL V-BANK COVER
  1. Engage the 2 hooks to install the V-bank cover to the No. 1 V-bank cover bracket.

  1. Align the 2 cushions of the V-bank cover with the 2 pins and press down on the V-bank cover to engage the 2 cushions to the 2 pins.

← INSTALLATION (Aug 2009 – Jul 2014)ON-VEHICLE INSPECTION (from Jul 2007) →