INTAKE MANIFOLD > INSTALLATION |
| 1. INSTALL STUD BOLT |
Using "Torx" socket wrench E8, install the 2 stud bolts to the intake manifold.
| 2. INSTALL INTAKE MANIFOLD |
![]() |
Install the new No. 1 intake manifold to head gasket and No. 2 intake manifold to head gasket to the cylinder head sub-assembly.
| *1 | No. 1 Intake Manifold To Head Gasket |
| *2 | No. 2 Intake Manifold To Head Gasket |
| *a | Bank 2 Identification Mark |
![]() | Front of Vehicle |
Temporarily install the intake manifold to the cylinder head sub-assembly with the 4 nuts and 6 bolts.
![]() |
Install and uniformly tighten the 4 nuts and 6 bolts in several steps in the sequence shown in the illustration.
Install the wire harness clamp bracket to the intake manifold with the bolt.
| 3. INSTALL FUEL DELIVERY PIPE SUB-ASSEMBLY |
![]() |
Place the fuel delivery pipe together with the 6 fuel injectors on the intake manifold.
| *a | Turn |
Temporarily install the 6 bolts, which are used to hold the fuel delivery pipe, to the intake manifold.
Check that the fuel injectors rotate smoothly.
Position the fuel injector connectors facing outward.
Tighten the 6 bolts, which are used to hold the fuel delivery pipe, to the intake manifold.
Connect the 6 fuel injector connectors.
| 4. CONNECT NO. 2 FUEL PIPE SUB-ASSEMBLY |
Connect the No. 2 fuel pipe sub-assembly (Click here).
| 5. CONNECT NO. 1 FUEL PIPE SUB-ASSEMBLY |
Connect the No. 1 fuel pipe sub-assembly (Click here).
| 6. INSTALL REAR CYLINDER HEAD COVER |
Temporarily install the cover with the 3 bolts.
![]() |
Tighten the 3 bolts in the sequence shown in the illustration.
| 7. INSTALL INTAKE AIR SURGE TANK |
![]() |
Install a new air surge tank to intake manifold gasket to the intake air surge tank.
Using an 8 mm socket hexagon wrench, temporarily install the intake air surge tank to the intake manifold with the 4 bolts and 2 nuts.
![]() |
Using an 8 mm socket hexagon wrench, install and uniformly tighten the 4 bolts and 2 nuts in several steps in the sequence shown in the illustration.
![]() |
Install the throttle body bracket to the intake air surge tank with the 2 bolts in the order shown in the illustration.
![]() |
Install the No. 1 surge tank stay to the intake air surge tank with the 2 bolts in the order shown in the illustration.
Engage the clamp and connect the wire harness to the No. 1 surge tank stay.
![]() |
Install the No. 2 surge tank stay to the intake air surge tank with the 2 bolts in the order shown in the illustration.
Connect the wire harness clamp bracket to the No. 2 surge tank stay with the bolt.
![]() |
Connect the No. 1 ventilation hose to the intake air surge tank with the hose clip.
| *a | View A |
| *b | Hose Paint Mark |
| *c | Front of Vehicle |
![]() |
Connect the No. 1 fuel vapor feed hose to the vacuum switching valve with the hose clip.
| *a | View A |
| *b | Hose Paint Mark |
| *c | Upper of Vehicle |
Connect the No. 1 vacuum switching valve connector.
Connect the 2 clamps of the heater water hose to the intake air surge tank.
![]() |
Connect the No. 4 water by-pass hose and No. 5 water by-pass hose to the water inlet housing with the 2 clips.
| *a | View A |
| *b | Hose Paint Mark |
| *c | Front of Vehicle |
Connect the throttle with motor body assembly connector.
| 8. INSTALL AIR HOSE ASSEMBLY (w/ Secondary Air Injection System) |
![]() |
Install the air hose assembly to the No. 2 emission control valve set with the hose clip.
| *a | View A |
| *b | Hose Paint Mark |
| *c | Upper of Vehicle |
| *d | Protrusion of No. 2 Emission Control Valve Set |
Connect the air hose assembly to the timing chain cover sub-assembly and No. 1 surge tank stay with the 2 bolts.
![]() |
Connect the air hose assembly to the No. 1 emission control valve set with the hose clip.
| *a | View A |
| *b | Hose Paint Mark |
| *c | Upper of Vehicle |
| *d | Protrusion of No. 1 Emission Control Valve Set |
Connect the air hose assembly to the timing chain cover sub-assembly with the bolt.
| 9. CONNECT NO. 1 AIR INJECTION SYSTEM HOSE (w/ Secondary Air Injection System) |
![]() |
Connect the No. 1 air injection system hose to the air hose assembly with the hose clip.
| *a | View A |
| *b | Hose Paint Mark |
| *c | Upper of Vehicle |
| *d | Protrusion of Air Hose Assembly |
| 10. INSTALL AIR CLEANER HOSE ASSEMBLY |
![]() |
Install the air cleaner hose assembly to the air cleaner cap sub-assembly and intake air surge tank with the 2 hose clamps.
| *a | View A |
| *b | View B |
| *c | Hose Paint Mark |
| *d | Upper of Vehicle |
| *e | Protrusion of Air Cleaner Cap Sub-assembly |
| *f | Protrusion of Intake Air Surge Tank |
| *g | Indentation of Air Hose Assembly |
Connect the air cleaner hose assembly to the resonator bracket with the bolt.
Engage the clamp and connect the wire harness to the air cleaner hose assembly.
Connect the vacuum hose to the air cleaner hose assembly.
Connect the ventilation hose to the air cleaner hose assembly with the hose clip.
| 11. ADD ENGINE COOLANT |
Tighten the cylinder block drain cock plug.
Tighten the radiator drain cock plug by hand.
Remove the vinyl hose from the radiator drain cock of the radiator assembly.
Add engine coolant.
| Item | Specified Condition |
| for Automatic Transmission | 9.8 liters (10.4 US qts, 8.6 Imp. qts) |
| for Manual Transmission | 9.4 liters (9.9 US qts, 8.3 Imp. qts) |
![]() |
Slowly pour engine coolant into the radiator reservoir until it reaches the Full line.
| *a | Full Line |
Install the radiator reserve tank cap sub-assembly.
Install the radiator cap sub-assembly.*1
Start the engine and stop it immediately.*2
Allow approximately 10 seconds to pass, and then remove the radiator cap sub-assembly and check the engine coolant level. If the engine coolant level has decreased, add engine coolant.*3
Repeat steps *1, *2 and *3 until the engine coolant level does not decrease.
Install the radiator cap sub-assembly.*4
Set the air conditioning as follows.*5
| Item | Condition |
| Fan speed | Any setting except off |
| Temperature | Toward WARM |
| Air conditioning switch | Off |
Start the engine, warm it up until the thermostat opens, and then continue to run the engine for several minutes to circulate the engine coolant.*6
Stop the engine, wait until the engine coolant cools down to ambient temperature, and then remove the radiator cap sub-assembly and check the engine coolant level.*7
If the engine coolant level has decreased, add engine coolant and warm up the engine until the thermostat opens.*8
![]() |
If the engine coolant level has not decreased, check that the engine coolant level in the radiator reservoir is at the Full line.
If the engine coolant level is below the Full line, repeat steps *4 through *8.
If the engine coolant level is above the Full line, drain engine coolant until the engine coolant level reaches the Full line.
| *a | Full Line |
Install the service hole cover to the engine under cover.
| 12. INSPECT FOR COOLANT LEAK |
Fill the radiator with engine coolant, and then attach a radiator cap tester.
Warm up the engine.
![]() |
Using the radiator cap tester, increase the pressure inside the radiator to 123 kPa (1.3 kgf/cm2, 18 psi), and then check that the pressure does not drop.
If the pressure drops, check the hoses, radiator and water pump for leakage. If there are no signs or traces of external engine coolant leakage, check the heater core, cylinder block and head.
| *1 | Radiator Cap Tester |
| 13. INSPECT FOR FUEL LEAK |
Connect the Techstream to the DLC3.
Turn the ignition switch to ON.
Turn the Techstream on.
Enter the following menus: Powertrain / Engine and ECT / Active Test / Control the Fuel Pump Speed / ON.
Check fuel pump operation.
Check for pressure in the fuel inlet tube from the fuel line. Check that the sound of fuel flowing in the fuel tank can be heard.
If there is no sound, check the integration relay, fuel pump, ECM and wiring connector.
| 14. INSTALL V-BANK COVER |
Engage the 2 hooks and install the V-bank cover to the No. 1 V-bank cover bracket.
Align the 2 V-bank cover grommets with the 2 pins and press down on the V-bank cover to engage the pins.
| 15. INSPECT INTAKE SYSTEM |