INSTALLATION
Removal / installation · Vehicles built Apr 2016 – Dec 2016
Versions by build date: Oct 2014 – Mar 2016 Apr 2016 – Dec 2016 from Jan 2017
| 1. INSTALL CLUTCH SWITCH ASSEMBLY |
Using a 14 mm union nut wrench, install the clutch switch assembly.
- Torque:
- 16 N*m{ 160 kgf*cm , 12 ft.*lbf }
- NOTICE:
- Use the formula to calculate special torque values for situations where a union nut wrench is combined with a torque wrench (Click here).
Connect the clutch switch connector.
| 2. INSPECT AND ADJUST CLUTCH PEDAL HEIGHT |
| 3. INSTALL NO. 1 AIR DUCT |
| 4. INSTALL LOWER CENTER INSTRUMENT PANEL FINISH PANEL |
Attach the 8 claws to install the instrument panel finish panel lower center.
| 5. INSTALL SHIFTING HOLE COVER ASSEMBLY |
for Manual Transmission:
Attach the 6 claws to install the shifting hole cover assembly.
for Automatic Transmission:
Attach the 8 claws to install the shifting hole cover assembly.
| 6. INSTALL SHIFT LEVER KNOB |
| 7. INSTALL PARKING BRAKE HOLE COVER |
Attach the 6 claws to install the parking brake hole cover.
| 8. INSTALL NO. 1 INSTRUMENT PANEL UNDER COVER SUB-ASSEMBLY |
Attach the 3 claws to instrument panel under cover sub-assembly No. 1.
Install the the 2 clips.
| 9. INSTALL LOWER INSTRUMENT PANEL FINISH PANEL |
Connect the fuel lid lock control cable and bonnet (hood) control cable assembly to the instrument panel finish lower.
Attach the 4 clips to install the instrument panel finish panel lower.
Install the 2 clips.
| 10. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL |
- Torque:
- 5.4 N*m{ 55 kgf*cm , 47 in.*lbf }
| 11. PERFORM INITIALIZATION |