85532
1.INSTALL USB CHARGER SOCKET
|
Install in this Direction |
Engage the 4 claws to install the USB charger socket as shown in the illustration.
85535B
2.INSTALL NO. 1 POWER OUTLET SOCKET COVER
|
Install in this Direction |
Engage the 2 claws to install the No. 1 power outlet socket cover as shown in the illustration.
85530
3.INSTALL NO. 1 POWER OUTLET SOCKET ASSEMBLY
|
Install in this Direction |
Engage the claw to install the No. 1 power outlet socket assembly as shown in the illustration.
55434F
4.INSTALL LOWER CENTER INSTRUMENT PANEL FINISH PANEL
55012B
5.INSTALL NO. 2 INSTRUMENT PANEL GARNISH SUB-ASSEMBLY
55011B
6.INSTALL NO. 1 INSTRUMENT PANEL GARNISH SUB-ASSEMBLY
55403G
7.INSTALL NO. 2 LOWER INSTRUMENT PANEL PAD SUB-ASSEMBLY
55402E
8.INSTALL NO. 1 LOWER INSTRUMENT PANEL PAD SUB-ASSEMBLY
9.INSTALL CONSOLE PANEL SUB-ASSEMBLY
33504F
10.INSTALL SHIFT LEVER KNOB SUB-ASSEMBLY
for UA80E: Click hereDrivetrain>UA80E (AUTOMATIC TRANSMISSION / TRANSAXLE)>SHIFT LEVER KNOB>INSTALLATION
for UA80F: Click hereDrivetrain>UA80F (AUTOMATIC TRANSMISSION / TRANSAXLE)>SHIFT LEVER KNOB>INSTALLATION
for P810: Click hereDrivetrain>P810 (HYBRID TRANSMISSION / TRANSAXLE)>SHIFT LEVER KNOB>INSTALLATION
58818A
11.INSTALL FRONT CONSOLE BOX COVER
58871
12.INSTALL CONSOLE BOX CUSHION
58872A
13.INSTALL NO. 2 CONSOLE BOX CUSHION