COMMON RAIL (w/ EGR Cooler) > INSTALLATION |
| 1. INSTALL COMMON RAIL ASSEMBLY |
w/o Pressure Discharge Valve:
![]() |
Install the common rail and No. 2 intake manifold insulator with the 2 bolts.
Connect the connector.
w/ Pressure Discharge Valve:
![]() |
Install the common rail and No. 2 intake manifold insulator with the 2 bolts.
Connect the 2 connectors.
| 2. INSTALL FUEL INLET PIPE SUB-ASSEMBLY |
![]() |
Temporarily install the fuel inlet pipe with the union nuts.
) Install a new O-ring to the oil level gauge guide, and install the oil level gauge guide to the cylinder block.
![]() |
Temporarily install the stay of the oil level gauge guide to the intake manifold with the bolt.
![]() |
Install the clamp with the bolt.
Tighten the bolt of the oil level gauge guide stay.
![]() |
Using a 17 mm union nut wrench, tighten the injection pipe union nut on the common rail side.
Using a 17 mm union nut wrench, tighten the injection pipe union nut on the supply pump side.
| 3. INSTALL NO. 2 NOZZLE LEAKAGE PIPE ASSEMBLY |
![]() |
Temporarily install the leakage pipe with the 3 bolts.
Temporarily install a new gasket with the check valve.
Tighten the 3 bolts and check valve.
Connect the 3 fuel hoses.
| 4. INSTALL NO. 4 INJECTION PIPE SUB-ASSEMBLY |
![]() |
Temporarily install the No. 4 injection pipe with the union nuts.
Install the bolt.
![]() |
Using a 17 mm union nut wrench, tighten the injection pipe union nuts on the common rail side.
Using a union nut wrench, tighten the injection pipe union nuts on the injector side.
| 5. INSTALL EGR COOLER WITH ELECTRIC EGR CONTROL VALVE AND NO. 2 EGR VALVE |
Install the EGR cooler with electric EGR control valve and No. 2 EGR valve (Click here).
| 6. INSTALL NO. 1, NO. 2 AND NO. 3 INJECTION PIPE SUB-ASSEMBLY |
Temporarily install the No. 1, No. 2 and No. 3 injection pipes with the union nuts.
![]() |
Install the No. 2 and No. 3 injection pipe clamps with the 2 bolts and 2 nuts, as shown in the illustration.
![]() |
Using a 17 mm union nut wrench, tighten the injection pipe union nuts on the common rail side.
Using a 17 mm union nut wrench, tighten the injection pipe union nuts on the injector side.
| 7. INSTALL OIL FILTER SUB-ASSEMBLY |
Check and clean the oil filter installation surface.
Apply clean engine oil to the gasket of a new oil filter.
Lightly screw the oil filter into place by hand. Tighten it until the gasket contacts the seat.
![]() |
Using SST, tighten the oil filter. Depending on the work space available, choose from the following.
If enough space is available, use a torque wrench to tighten the oil filter.
If enough space is not available to use a torque wrench, tighten the oil filter 3/4 turn by hand or with a common wrench.
| 8. INSTALL MANIFOLD STAY WITH VACUUM SWITCHING VALVE |
![]() |
Install the stay with the 2 bolts.
Connect the 3 vacuum hoses to the 2 VSV.
| 9. INSTALL INTERCOOLER ASSEMBLY |
Install the intercooler assembly (Click here).
| 10. INSTALL FUEL TANK CAP ASSEMBLY |
| 11. ADD ENGINE OIL |
Wipe the oil pan and drain plug.
Install a new gasket and the drain plug.
Add new oil.
| Item | Specified Condition |
| Drain and refill with oil filter change | 6.9 liters (7.3 US qts, 6.1 Imp. qts) |
| Drain and refill without oil filter change | 6.6 liters (7.0 US qts, 5.8 Imp. qts) |
| Dry fill | 7.4 liters (7.8 US qts, 6.5 Imp. qts) |
Install the oil filler cap.
| 12. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL |
| 13. BLEED AIR FROM FUEL SYSTEM |
![]() |
Using the hand pump mounted on the fuel filter cap, bleed the air from the fuel system. Continue pumping until the pump resistance increases.
Start the engine.
When the engine can be started, proceed to the next step.
If the engine cannot be started, bleed the air again using the hand pump until the hand pump resistance increases (refer to the procedures above). Then start the engine.
Turn the ignition switch off.
Connect the intelligent tester to the DLC3.
Turn the ignition switch to ON and turn the intelligent tester on.
Clear the DTCs (Click here).
Start the engine.*1
![]() |
Enter the following menus: Powertrain / Engine and ECT / Active Test / Test the Fuel Leak.*2
Perform the following test 5 times with on/off intervals of 10 seconds: Active Test / Test the Fuel Leak.*3
Allow the engine to idle for 3 minutes or more after performing the Active Test for the fifth time.

Enter the following menus: Powertrain / Engine and ECT / DTC.
Read Current DTCs.
Clear the DTCs (Click here).
Repeat steps *1 to *3.
Enter the following menus: Powertrain / Engine and ECT / DTC.
Read Current DTCs.
| 14. INSPECT FOR OIL LEAK |
| 15. INSPECT FOR FUEL LEAK |
![]() |
Check that there are no leaks from any part of the fuel system when the engine is stopped.
If there is fuel leakage, repair or replace parts as necessary.
Start the engine and check that there are no leaks from any part of the fuel system.
If there is fuel leakage, repair or replace parts as necessary.
Disconnect the return hose from the common rail.
Start the engine and check for fuel leaks from the return pipe.
If there is fuel leakage, replace the common rail.
Connect the intelligent tester to the DLC3.
Start the engine and push the intelligent tester main switch ON.
Select the Fuel Leak test from the Active Test mode on the intelligent tester.
If the intelligent tester is not available, fully depress the accelerator pedal quickly. Increase the engine speed to the maximum and maintain that speed for 2 seconds. Repeat this operation several times.
Check that there are no leaks from any part of the fuel system.
Reconnect the return hose to the common rail.
| 16. REMOVE NO. 2 ENGINE UNDER COVER |
Install the under cover with the 4 bolts.
| 17. REMOVE NO. 1 ENGINE UNDER COVER |
Install the under cover with the 4 bolts.