2014 Hilux · Service Manual ENGINE

INSTALLATION

Removal / installation · Vehicles built Aug 2012 – Jul 2013

Versions by build date: Jun 2011 – Jul 2012 Aug 2012 – Jul 2013 from Aug 2013


1. INSTALL VENTILATION VALVE SUB-ASSEMBLY

A092670E03
  1. Apply adhesive to 2 or 3 threads of the valve.

    Adhesive:
    Toyota Genuine Adhesive 1324, Three Bond 1324 or equivalent

  1. A112001E01
    Install the valve.

    Torque:
    5.0 N*m{ 51 kgf*cm , 44 in.*lbf }

  1. Connect the ventilation hose to the valve.

  1. Secure the hose with the clamp.


2. INSTALL INTAKE AIR SURGE TANK

A075648E01
  1. Install a new gasket and the surge tank with the 2 nuts.

    Torque:
    28 N*m{ 286 kgf*cm , 21 ft.*lbf }

  1. Using an 8 hexagon wrench, install the 4 bolts.

    Torque:
    28 N*m{ 286 kgf*cm , 21 ft.*lbf }

  1. A075647E01
    Install the 3 upper bolts which are used to secure the 2 surge tank stays and throttle body bracket.

    Torque:
    21 N*m{ 214 kgf*cm , 16 ft.*lbf }

  1. A075646E01
    Install the 3 wire harness clamps and hose clamp.

  1. Connect the throttle motor connector.

  1. Connect the 2 VSV connectors.

  1. A075645E01
    Connect the ventilation hose.

  1. A075644E01
    Connect the vapor feed hose assembly.

  1. A075598E01
    Connect the No. 4 water by-pass hose.

  1. A075597E01
    Connect the No. 5 water by-pass hose.


3. INSTALL V-BANK COVER
  1. Install the cover with the 2 nuts.

    Torque:
    7.5 N*m{ 76.5 kgf*cm , 66 in.*lbf }


4. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

5. PERFORM INITIALIZATION
  1. Perform initialization (Click here).

    NOTICE:
    Certain systems need to be initialized after disconnecting and reconnecting the cable from the negative (-) battery terminal.

← INSTALLATION (Jun 2011 – Jul 2012)INSTALLATION (from Aug 2013) →