2011-2013 Land Cruiser · Service Manual Power Source / Network

REASSEMBLY

Removal / installation · Vehicles built Sep 2011 – Dec 2011


1. INSTALL GENERATOR ROTOR ASSEMBLY

  1. A117223
    Place the drive end frame on the pulley.

  1. Install the rotor to the drive end frame.


2. INSTALL GENERATOR COIL ASSEMBLY

  1. A117224E01
    Place the generator washer on the rotor.

  1. A177984
    Using a 21 mm socket wrench and a press, slowly press in the coil assembly.

  1. A177978
    Install the 4 bolts.

    Torque:
    5.9 N*m{ 60 kgf*cm , 52 in.*lbf }


3. INSTALL GENERATOR BRUSH HOLDER ASSEMBLY

  1. A163049E01
    While pushing the 2 brushes toward the inside of the brush holder, insert a pin (diameter 1.0 mm (0.0394 in.)) into the brush holder hole.

  1. A177985E01
    Install the generator brush holder with the 2 screws.

    Torque:
    1.8 N*m{ 18 kgf*cm , 16 in.*lbf }

  1. Pull out the pin from the generator brush holder.


4. INSTALL GENERATOR REAR END COVER

  1. A177976
    Install the terminal insulator to the generator rectifier end frame.

    NOTICE:
    Pay attention to the mounting orientation of the terminal insulator.

  1. A180125
    Install the end cover with the 3 nuts.

    Torque:
    4.6 N*m{ 46 kgf*cm , 40 in.*lbf }


5. INSTALL GENERATOR PULLEY

A162627E01
SST
09820-63011   (09820-06010, 09820-06021)

HINT:
SST 1-A and B
09820-06010
SST 2
09820-06021

  1. Install the pulley onto the rotor shaft by tightening the pulley nut by hand.

  1. Hold SST 1-A with a torque wrench, and tighten SST 1-B clockwise to the specified torque.

    Torque:
    39 N*m{ 398 kgf*cm , 29 ft.*lbf }

    NOTICE:
    Check that SST is secured to the rotor shaft.

  1. B016524E04
    Mount SST 2 in a vise.

  1. Insert SST 1-A and B into SST 2, and attach the pulley nut to SST 2.

  1. B016523E03
    Tighten the pulley nut by turning SST 1-A in the direction shown in the illustration.

    Torque:
    133 N*m{ 1351 kgf*cm , 98 ft.*lbf }

  1. Remove the generator from SST 2.

  1. A162628E01
    Turn SST 1-B, and remove SST 1-A and B.

  1. Turn the pulley and check that the pulley moves smoothly.

← INSPECTION (Sep 2011 – Dec 2011)INSTALLATION (Sep 2011 – Dec 2011) →