INSTALLATION

Removal / installation · Vehicles built from Jan 2012

Versions by build date: Sep 2011 – Dec 2011 from Jan 2012


1. INSTALL PCV VALVE SUB-ASSEMBLY
  1. Apply adhesive to 2 or 3 threads of the PCV valve.

    Adhesive:
    Toyota Genuine Adhesive 1324, Three Bond 1324 or equivalent

  1. Install the PCV valve.

    Torque:
    27 N*m{ 275 kgf*cm , 20 ft.*lbf }

  1. Connect the PCV hose to the valve.

  1. Secure the hose with the clamp.


2. INSTALL V-BANK COVER

  1. A271365E01
    Attach the 2 V-bank cover hooks to the bracket. Then align the 2 V-bank cover grommets with the 2 pins and press down on the V-bank cover to attach the pins.
    Text in Illustration 
    *1
    Pin
    *2
    Hook