2011-2013 Land Cruiser · Service Manual Engine / Hybrid / EV System

INSTALLATION

Removal / installation · Vehicles built Sep 2011 – Dec 2011

Versions by build date: Sep 2011 – Dec 2011 from Jan 2012


1. INSTALL PCV VALVE SUB-ASSEMBLY

  1. A158640E02
    Apply a light coat of engine oil to the O-ring of the valve.
    Text in Illustration 
    *1
    O-Ring

    HINT:
    When reusing the PCV valve, inspect the O-ring. If the O-ring has scratches or cuts, replace the PCV valve.

  1. Install the PCV valve.

    Torque:
    3.5 N*m{ 36 kgf*cm , 31 in.*lbf }


2. INSTALL PCV VALVE HOSE
  1. Install the hose to the PCV valve.


3. INSTALL NO. 2 ENGINE COVER

4. INSTALL INTAKE MANIFOLD